Roads and Land Works
Amaravati Road Works Move Seven Old Trees Instead of Felling Them, Keeping the Seed Access Corridor Going
The Amaravati Development Corporation has directed that seven mature trees blocking an elevated corridor at Sitanagaram be uprooted with their root systems and replanted, rather than cut down, so that Seed Access Road Phase-3 can continue. The works cover a 3.4 km stretch between Undavalli and the Tadepalli bridge, in the capital region that is Under Construction as of November 2026.

| Authority | Amaravati Development Corporation (ADC) |
|---|---|
| Directive issued by | D. Lakshmi Parthasarathi, chairperson and managing director |
| Location of trees | Sitanagaram, near the boating yard |
| Project stretch | 3.4 km between Undavalli and the Tadepalli bridge |
| Trees affected | Seven mature trees, mainly peepal and neem, estimated at about 50 years old |
| Relocation site | Sakhamuru Central Park |
| Works status | Ongoing as of 21 November 2026; no completion date reported |
| Notified capital city area | 217.23 sq km across 25 villages in Thullur, Mangalagiri and Tadepalli mandals (as on 11 November 2026) |
What the directive decided
The chairperson and managing director of the Amaravati Development Corporation, D. Lakshmi Parthasarathi, directed officials to shift seven mature trees that stand in the path of an elevated corridor near the boating yard at Sitanagaram. Rather than cutting them, the trees are to be uprooted together with their root systems and replanted at Sakhamuru Central Park.
Most of the trees are peepal and neem, and they are estimated to be around 50 years old. Relocating mature trees of this kind is slower and more demanding than felling them, which is why the decision matters for the timing and cost of the corridor works, although no figures for either were reported.
The Seed Access Road Phase-3 works
The directive followed an inspection of the ongoing Seed Access Road Phase-3 works. The stretch covered is 3.4 km between Undavalli and the Tadepalli bridge, on the Krishna river side of the capital. The report does not give a completion date for the works.
The Seed Access Road network is the set of arterial links meant to connect the capital with Vijayawada and the wider road system. The Amaravati Seed Capital Road (E3) is a 21 km arterial flyover road in this network, running from Dondapadu at its west end to the Kanakadurga Varadhi junction on National Highway 16 at its east end.
Site checks on workers' wages
During the visit, the chairperson also spoke with construction workers about working hours and wage payment. The reported daily rates are Rs 1,000 for masons and Rs 800 for helpers, credited to bank accounts every Saturday.
For buyers and local families, site-level wage checks are a signal of how the capital's main road works are being supervised, a point that matters when large projects draw in workers from across the region.
What this means for the capital's roads and growth
For the city, the choice to relocate rather than cut the trees keeps a planned road link moving without a fresh break in the capital's road plan. Better road links are one of the basic conditions for turning the land now being assembled into usable plots, homes and offices.
The road works sit within a larger capital programme. Phase 1 of the capital drew about 34,000 acres from farmers under the voluntary Land Pooling Scheme (as on 11 November 2026). A separate railway line with nine stations, including a main station at Amaravati, is being aligned across the capital. Earlier reports cite a 57 km line at Rs 2,245 crore over four years, approved by the Union Cabinet on 24 October 2024.
Growth is not uniform across the capital. On 16 November 2026, farmers said residential and commercial plots returned to them in 13 land pooling zones still lacked roads, drainage, electricity and water. Road progress like the Seed Access Road Phase-3 works is therefore watched closely by landowners in those zones.
Where the capital's plan stands
Amaravati is the purpose-built capital of Andhra Pradesh, laid out on the right bank of the Krishna river in Guntur district, about 15 km southwest of Vijayawada. It is planned and built by the Andhra Pradesh Capital Region Development Authority (APCRDA), working with the Amaravati Development Corporation Limited. A 2026 Parliament law names Amaravati the sole and permanent capital of the state.
The notified capital city area is 217.23 sq km across 25 villages in Thullur, Mangalagiri and Tadepalli mandals, within a wider capital region of 8,352.69 sq km across six districts (as on 11 November 2026).
What comes next
The directive asks officials to carry out the uprooting and replanting at Sitanagaram and Sakhamuru Central Park. The report does not give a timeline for the relocation, and works on the 3.4 km stretch remain ongoing as of 21 November 2026. Future updates on the Seed Access Road Phase-3 works will show whether the corridor near the boating yard proceeds as planned.
Frequently asked questions
Where is the Amaravati Seed Access Road Phase-3 being built?
The Seed Access Road Phase-3 works cover a 3.4 km stretch between Undavalli and the Tadepalli bridge, with an elevated corridor near the boating yard at Sitanagaram.
Why are the seven trees at Sitanagaram being moved?
Seven mature trees, mainly peepal and neem, block the elevated corridor, and the Amaravati Development Corporation directed that they be uprooted with their root systems and relocated rather than cut down.
Where will the trees be replanted?
The trees are to be replanted at Sakhamuru Central Park, according to the directive from the Amaravati Development Corporation's chairperson and managing director.
What is the length of the Amaravati Seed Capital Road?
The Amaravati Seed Capital Road (E3) is a 21 km arterial flyover road, running from Dondapadu to the Kanakadurga Varadhi junction on National Highway 16.
What daily wages were reported for workers on the Amaravati road works?
Masons were reported to earn Rs 1,000 per day and helpers Rs 800 per day, with wages credited to bank accounts every Saturday.
Sources
- 7 mature trees to be relocated for Amaravati road project
- Amaravati Seed Capital Road - Wikipedia
- Amaravati - Wikipedia
- Andhra Pradesh Capital Region Development Authority - Wikipedia
- Amaravati to now be permanent capital of Andhra Pradesh (Akashvani News)
- Amaravati mega railway station route finalized, track to support 160 kmph speed
- APCRDA - Amaravati Master Plans