Railway Development
Amaravati Railway Line: Land Acquisition Begins for 57-km Errupalem–Namburu Connector
The long-awaited ₹2,047 crore Errupalem–Amaravati–Namburu 57 km new broad-gauge railway line gained fresh momentum in early August 2026 as land acquisition work started, with the project having been sanctioned by the Union Cabinet in 2024. Railway authorities have begun the process to acquire nearly 300 acres of land across eight villages in NTR district—Gottumukkala, Paritala, Jujjuru, G. Madhavaram, Chennaraopalem, Peddapurum, Alluru and Narasimharao Palem—in coordination with the state revenue machinery.

| Project Cost (Union Cabinet Approval) | ₹2,047 crore (per brief); ₹2,245 crore (Cabinet announcement) |
|---|---|
| Line Length | 57 km (56.53 km precise) |
| Route | Errupalem (Khammam, Telangana) to Namburu (Guntur, AP) via Amaravati |
| Current Land Acquisition Status (August 2026) | Started; 300 acres needed in NTR district across 8 villages |
| New Railway Stations | 9 stations: Peddapuram, Chinnaravupalem, Gottumukkala, Paritala, Kothapeta, Vaddamanu, Amaravati, Tadikonda, Koppuravuru |
| Krishna River Bridge | 3.0–3.2 km long railway bridge required |
| Population Coverage | Approximately 168 villages; 12 lakh people via 9 stations |
| Administrative Authority | South Central Railway (SCR); Andhra Pradesh Capital Region Development Authority (APCRDA/CRDA) for land provision |
| Cabinet Approval Date | 24 October 2024 |
| Union Minister Handling | Ashwini Vaishnaw (Railways); tabled project in Parliament monsoon session 2024 |
What Happened: Land Acquisition Begins
Railway authorities have begun the process to acquire nearly 300 acres of land across eight villages in NTR district, with the acquisition being carried out in coordination with the state revenue machinery. The villages covered are Gottumukkala, Paritala, Jujjuru, G. Madhavaram, Chennaraopalem, Peddapurum, Alluru and Narasimharao Palem in Kanchikacherla and Veeralapadu mandals.
Approximately 80% of the required land is already available through the Capital Region Development Authority (CRDA), with only a small portion needing to be acquired in NTR district. SCR plans to acquire 60 acres of land in Yerrupalem and Kesireddypalle villages, with a draft notification issued for farmers to file objections. Farmers in the affected areas have been given 30 days to submit objections to the land acquisition.
Why: Cabinet Approval and Strategic Role
The new line will connect Andhra Pradesh's greenfield capital Amaravati directly to the national rail network and will also serve as a strategic bypass corridor and help reduce heavy traffic congestion at Vijayawada Junction.
The estimated cost of this project is 2,245 crore rupees and will provide direct rail connectivity to Hyderabad, Chennai and Kolkata. These projects will generate direct employment for approximately 106 lakh human-days.
Stations and Infrastructure
This new railway line will have a total of 9 stations, including Peddapuram, Chinnaravupalem, Gottumukkala, Paritala, Kothapeta, Vaddamanu, Amaravathi, Tadikonda, and Koppuravuru, with Amaravati being the main station.
One of the key features of this project is the construction of a 3KM long bridge over the Krishna river between Kothapeta and Vaddamanu.
A multi-modal cargo station is also planned for Paritala in NTR district, which is expected to become a critical freight hub along the new route. The Andhra Pradesh government has also requested the Ministry of Railways to develop the Amaravati station as a model railway station, proposing around 1,500 acres for its development.
Project Timeline
While the central government has set a four-year timeline for completion, Andhra Pradesh Chief Minister Chandrababu Naidu has urged for faster progress, requesting that the project be completed within three years. As the land acquisition is at pace, the project will move into the execution stage.
Regional Coverage and Impact
The Errupalem–Amaravati–Namburu line will pass through NTR, Vijayawada and Guntur districts of Andhra Pradesh and Khammam district of Telangana, and will provide rail connectivity to approximately 168 villages and about 12 lakh people through nine new stations.
Development phases
Frequently asked questions
Why did this railway project take so long to start construction?
The project was pending for years because of delays in land acquisition.
Who approved this project and when?
The project was sanctioned by the Union Cabinet in 2024. The Cabinet approval was announced on 24 October 2024.
How much land needs to be acquired?
Railway authorities have begun the process to acquire nearly 300 acres of land across eight villages in NTR district. Approximately 80% of the required land is already available through the Capital Region Development Authority (CRDA), with only a small portion needing to be acquired in NTR district.
What is the project cost?
The ₹2,047 crore Errupalem–Amaravati–Namburu 57 km new broad-gauge railway line gained fresh momentum in early August 2026. The Union Cabinet announced a cost of ₹2,245 crore.
Who can object to land acquisition?
Farmers in the affected areas have been given 30 days to submit objections to the land acquisition.
What does this railway line do for Amaravati?
The new line will connect Andhra Pradesh's greenfield capital Amaravati directly to the national rail network and will also serve as a strategic bypass corridor and help reduce heavy traffic congestion at Vijayawada Junction.
How long will it take to complete?
While the central government has set a four-year timeline for completion, Andhra Pradesh Chief Minister Chandrababu Naidu has urged for faster progress, requesting that the project be completed within three years.
Sources
- Metro Rail News: Amaravati to Join National Rail Network — Land Acquisition Started for Errupalem–Amaravati–Nambur Railway Line
- The Hans India: Errupalem-Amaravati Nambur Railway Line Gets Nod, Land Acquisition Notification Issued
- Deccan Chronicle: Union Cabinet Approves Railway Connectivity to Amaravati
- Wikipedia: Errupalem–Amaravathi–Nambur Railway Line
- Construction World: Land Acquisition Started for Rs 22.45 Billion Amaravati Railway Line
- Swarajya: Amaravati Railway Line — Land Acquisition Begins for Rs 2,245 Crore Project
- News on Air: Cabinet Approves ₹6,798 Crore Rail Projects to Boost Connectivity
- News on Air: Andhra CM Expresses Happiness Over Cabinet's Approval for New Amaravati Railway Line