World Bank and ADB may add Rs 15,000 crore for Amaravati; CRDA seeks new project management consultant
The World Bank and the Asian Development Bank are reported to be preparing an extra Rs 15,000 crore for the Amaravati capital programme, with money released as construction advances. The Capital Region Development Authority has also invited bids for a new programme management consultant because the current one's contract ends in January 2027.

| Region and state | Amaravati (Amaravati Capital City), Andhra Pradesh |
|---|---|
| Development authority | APCRDA (Capital Region Development Authority, CRDA) |
| Additional funding reported | Rs 15,000 crore, with Rs 7,500 crore each from the World Bank and ADB (reports dated 17 October 2026) |
| Approval status | In its final stages, as of 17 October 2026 reports |
| First-phase deadline | 2029 |
| Disbursement period | Phased release until 2031, linked to construction progress |
| Projects underway | 102 projects worth Rs 52,362.44 crore (CRDA figure) |
| Projects planned | 141 projects with an estimated outlay of Rs 1,00,912 crore (CRDA figure) |
| Consultant tenure ends | January 2027 for the existing programme management consultant |
What has been reported
The World Bank and the Asian Development Bank (ADB) will provide an additional Rs 15,000 crore to build Amaravati, Andhra Pradesh's capital. The two institutions are expected to contribute Rs 7,500 crore each, with the approval process in its final stages.
The money is expected to flow over several years rather than in one transfer. The funds will be released in phases until 2031. The reports also link each payment to physical progress on the ground: fund disbursement is linked to construction progress.
Reports describe the funds as a top-up to an earlier tranche. The two banks have already sanctioned an initial tranche of Rs 15,000 crore, which is being used for various development works in the capital city.
Consultant tender and oversight
Alongside the funding news, the CRDA has moved to replace its oversight consultant. The Capital Region Development Authority (CRDA) has invited tenders to appoint a Programme Management Consultancy (PMC) firm to oversee works funded by the World Bank, ADB and other financial institutions. The reason given is timing: the existing PMC's tenure ends in January 2027, prompting the CRDA to issue a new tender to appoint a new agency.
The role is significant because the programme is run through several layers. The programme documents describe a programme-level consultant supporting the APCRDA, with separate project consultants for each package. The APCRDA will be further supported by a Program Management Consultant (PgMC) for operational support and a Project Management Consultant (PMC) for each of the subprojects/packages. Reports on the new tender add that the appointee would oversee project implementation, financial management and compliance with prescribed standards.
Size of the works programme
The CRDA's own figures show a large pipeline. According to the CRDA, 102 projects worth Rs 52,362.44 crore are currently underway in the capital region. A wider set of plans is also on the table. The CRDA has drawn up plans for 141 projects in the capital region, with a combined estimated outlay of Rs 1,00,912 crore. While projects worth nearly Rs 52,362 crore are already underway, the remaining works will be taken up in phases.
Among the proposed works are river crossings. The proposed projects include an Iconic Bridge across the Krishna River connecting Amaravati and Ibrahimpatnam, and a Signature Bridge downstream of the Prakasam Barrage. For the Signature Bridge, the proposed Signature Bridge is estimated to cost Rs 650 crore. The CRDA said it would soon appoint a consultant to prepare the project's DPR.
Background to the bank funding
The current funding round builds on a 2024 agreement. The World Bank along with the Asian Development Bank in principle has committed to fund $1600 million (Rs 13, 600 crore) for Amaravati capital city phase-I development. The programme itself is titled the Amaravati Inclusive and Sustainable Capital City Development Program, and the World Bank's programme document records financing of US$800 million each from the World Bank and ADB.
Land is central to the scheme. The voluntary LPS (Land Pooling System) pooled 34,390 acres of farmland when Naidu was in power between 2014 and 2019, which is the land base on which much of the planned development sits.
What comes next
As of 22 October 2026, the additional Rs 15,000 crore is still described as being in the approval stage. The main near-term steps are:
- Selection of a new programme management consultant before the current contract ends in January 2027.
- Appointment of a consultant to prepare the detailed project report for the Signature Bridge.
- Continued construction under the 102 works already underway, with bank releases tied to progress.
- Completion of the first phase, which has a deadline of 2029.
The longer-term plan extends beyond that date, with the remaining planned works taken up in stages.
Development phases
Frequently asked questions
How much additional money is being reported for Amaravati?
Reports dated 17 October 2026 say the World Bank and ADB are expected to contribute Rs 15,000 crore in total, about Rs 7,500 crore each.
When will the funds be released?
The reports say the money will be released in phases until 2031, and each release is linked to construction progress.
Why is the CRDA tendering for a new consultant?
The existing programme management consultant's tenure ends in January 2027, so the CRDA has invited tenders for a replacement.
How big is the current Amaravati works programme?
The CRDA says 102 projects worth Rs 52,362.44 crore are underway, and 141 projects with an estimated outlay of Rs 1,00,912 crore have been planned.
Is the additional Rs 15,000 crore already sanctioned?
As of the 17 October 2026 reports, the approval process was described as being in its final stages.
Sources
- World Bank, ADB Set To Provide Additional Rs 15,000 Crore For Andhra Pradesh Capital Amaravati
- World Bank, ADB Back Additional Rs 15,000 Crore Loan Proposal for Amaravati Capital Construction
- Amaravati Capital City Development Programme (P507508) Environmental and Social Systems Assessment
- World Bank, ADB to release Rs 13,600 crore for Amaravati
- World Bank, ADB commit $1.6 bn for Andhra capital Amaravati from Jan 2025