Major Milestone

Drone Survey Completed for UP's First Integrated TOD Township in Meerut

Uttar Pradesh's first Integrated Transit-Oriented Development (TOD) Township has completed its drone survey, paving the way for detailed layout plan preparation. So far, 127 hectares of land have been purchased, with acquisitions underway in Mohiuddinpur, Chhajjupur, Ikla, and Kayasth Gaondi villages; development will be carried out in 31 sectors across two phases.

Meerut New Township (Mohiuddinpur) — Drone Survey Completed for UP's First Integrated TOD Township in Meerut
Total Site Area294 hectares in Mohiuddinpur along Delhi Road
Land Acquired (as of August 2025)127 hectares purchased; acquisitions ongoing in four villages
Development ModelMixed-use: residential, commercial, and industrial on different floors of same buildings
Project Structure31 sectors divided across two phases
Government Fund Allocation₹409 crores to MEDA
Status as of August 2025Drone survey complete; detailed layout plan being prepared
Road Construction DeadlineTwo sectors targeted for completion by November 2025
Planned LaunchDiwali 2025, with plot sales to commence
DeveloperMeerut Development Authority (MEDA)
Acquisition VillagesMohiuddinpur, Chhajjupur, Ikla, Kayasth Gaondi

Survey Completion Clears Path for Layout Planning

The drone survey for the state's first integrated TOD township in Meerut has been completed. The township, being developed by the Meerut Development Authority (MEDA) on 294 hectares in Mohiuddinpur along Delhi Road, will follow a mixed-use model with residential, commercial, and industrial activities on different floors of the same buildings. Based on the survey, a detailed layout plan will now be prepared.

Land Acquisition in Progress Across Four Villages

So far, 127 hectares of land have been purchased, with acquisitions underway in Mohiuddinpur, Chhajjupur, Ikla, and Kayasth Gaondi villages. In phase 1 of purchasing, the target is to buy 111 hectares of Mohiuddinpur and 30 hectares of Chhajjapur. In phase 2, Kayastha Gaongri and Ikla will be bought.

Mixed-Use Development with Plots for All Income Groups

The township will have plots available for people of all income groups. Development will be carried out in 31 sectors across two phases. This structure enables residential buyers, commercial businesses, and industrial operators to coexist within the same integrated development, maximizing land utilization near transit infrastructure.

Two Sectors on Track for November Completion

Work in two sectors is expected to be completed by November, with the township officially launched on Diwali when plot sales begin. MEDA plans to start by constructing wide arterial roads. These foundational roads will establish connectivity within the township and link to Delhi Road, a critical component before phased construction can proceed.

Positioning Within Meerut's Transit-Oriented Development Vision

The Meerut Masterplan 2031 is the first masterplan in India to formally embed Transit-Oriented Development (TOD) zones. The Mohiuddinpur township represents MEDA's flagship application of this model, leveraging proximity to transit corridors to reduce vehicle dependence and create a compact, mixed-income community. The Meerut Development Authority (MEDA) has earmarked approximately 3,273 hectares for TOD, with 2,442 hectares designated into seven TOD zones and two Special Development Area (SDA) zones.

Development phases

Phase 1: Land Acquisition & Layout Planning2025111 hectares in Mohiuddinpur, 30 hectares inChhajjupur. Drone survey completed, detailed layoutplanPhase 2: Land Acquisition Completion2025–2026Kayastha Gaongri and Ikla villages. Concurrent road andbasic infrastructure construction.Phase 1 Sector Developmentby November 2025Two sectors completion targeted, with arterial roadconstruction and formal township launch at Diwali.

Land use

Frequently asked questions

What does TOD (Transit-Oriented Development) mean?

Transit-Oriented Development (TOD) is an innovative urban paradigm that involves leveraging existing and upcoming public transit infrastructure and associated large number of users, to ensure sustainable mobility and optimise utilisation of land through compact mixed-use development.

Why is Meerut's approach significant?

The Meerut Masterplan 2031 is the first masterplan in India to formally embed Transit-Oriented Development (TOD) zones. The Mohiuddinpur township is the first operational implementation of this policy at state level.

When will plot sales begin?

The township officially launched on Diwali when plot sales begin. As of August 2025, the authority is targeting Diwali 2025 for the official launch and commencement of plot sales in initial sectors.

How much land has MEDA acquired so far?

So far, 127 hectares of land have been purchased, with acquisitions underway in Mohiuddinpur, Chhajjupur, Ikla, and Kayasth Gaondi villages. The total project size is 294 hectares.

What is the project structure?

Development will be carried out in 31 sectors across two phases. The township follows a mixed-use model with residential, commercial, and industrial activities on different floors of the same buildings.

What is the first construction priority?

MEDA plans to start by constructing wide arterial roads. These foundational roads establish internal connectivity and link the township to Delhi Road before plot construction commences.