MEDA Launches Land Acquisition for Integrated Township in Mohiuddinpur as Uttar Pradesh's First TOD Project

The Meerut Development Authority (MEDA) has initiated land acquisition for Uttar Pradesh's first integrated Transit-Oriented Development (TOD) township on 294 hectares in Mohiuddinpur along Delhi Road, following a mixed-use model with residential, commercial, and industrial activities.

Meerut New Township (Mohiuddinpur) — MEDA Launches Land Acquisition for Integrated Township in Mohiuddinpur as Uttar Pradesh's First TOD Project
Total Land Area294 hectares in Mohiuddinpur
Land Acquisition Status (as of April 2026)Over 150 hectares purchased across Mohiuddinpur, Chhajjupur, and Kayastha Gaondi villages
Total Land Acquisition CostRs. 1,086 crore
Development Zones31 sectors across two phases
Villages InvolvedMohiuddinpur, Chhajjupur, Ikla, and Kayasth Gaondi
Phase 1 Land Purchase Target111 hectares of Mohiuddinpur and 30 hectares of Chhajjupur
Land Use ModelMixed-use with residential, commercial, and industrial activities on different floors of same buildings
Development AuthorityMeerut Development Authority (MEDA)

What the Project Is

The Meerut Development Authority has launched Uttar Pradesh's first Integrated Transit-Oriented Development (TOD) Township, also called the New Township. The township will follow a mixed-use model with residential, commercial, and industrial activities on different floors of the same buildings. The project will be developed on 294 hectares in Mohiuddinpur along Delhi Road and will have plots available for people of all income groups.

Land Acquisition Timeline

MEDA began the land purchase process in May 2024 on a war footing with farmers from local villages. As of August 2025, 127 hectares of land had been purchased, with acquisitions underway in Mohiuddinpur, Chhajjupur, Ikla, and Kayasth Gaondi villages. By April 2026, the authority had completed acquisition of over 150 hectares: 46 hectares in Mohiuddinpur for Rs. 418 crore, 21 hectares in Chhajjupur for Rs. 81 crore, and 81 hectares in Daultpur Fakhrabad (Kayastha Gaondi) for Rs. 587 crore.

Development Structure

Development will be carried out in 31 sectors across two phases. Both sides of the township have been divided into 31 sectors. The township will feature residential, industrial, and commercial zones within the same premises. A detailed layout plan will be prepared based on drone survey, with the township following a mixed-use model combining residential, commercial, and industrial activities on different floors of the same buildings.

Transit Integration and Location

The township's location along Delhi Road positions it near transit infrastructure crucial to its TOD strategy. The Meerut Metro has commenced operations as India's fastest local metro system, sharing infrastructure with the RRTS to provide seamless intra-city and regional connectivity at speeds up to 120 kmph. Travel time between Delhi and Meerut has been reduced to under an hour with the regional rail corridor.

Next Steps

Work in two sectors is expected to be completed by November, with the township officially launched on Diwali when plot sales begin. MEDA plans to start by constructing wide arterial roads. The township will have plots available for people of all income groups.

Development phases

Phase 12024–2026Land acquisition: 111 hectares Mohiuddinpur + 30 hectaresChhajjupur; development in 2 initial sectorsPhase 22026 onwardsRemaining 31 sectors; continuing land acquisition; fulltownship completion

Land use

Residential45%Commercial20%Industrial20%Open Space &Infrastructure15%

Frequently asked questions

What makes this township different from other Meerut housing projects?

This is Uttar Pradesh's first Integrated Transit-Oriented Development (TOD) Township, featuring a mixed-use model where residential, commercial, and industrial activities are combined on different floors of the same buildings rather than in separate zones.

Which villages are affected by land acquisition?

Land acquisitions are underway in Mohiuddinpur, Chhajjupur, Ikla, and Kayasth Gaondi villages.

When will the township be ready for buyers?

Work in two sectors is expected to be completed by November, with the township officially launched on Diwali when plot sales begin.

What is the total investment for this project?

The government has sanctioned Rs. 409 crores to the Meerut Development Authority (MEDA). Land acquisition alone has cost Rs. 1,086 crore for over 150 hectares purchased.

Will this township be affordable for middle-income buyers?

The township will have plots available for people of all income groups.

How is the township connected to Delhi?

With the 82-km Delhi–Ghaziabad–Meerut Regional Rapid Transit System (RRTS) now fully operational from Sarai Kale Khan to Modipuram, travel time between Delhi and Meerut has reduced to under an hour.

Who is developing the township?

The Meerut Development Authority (MEDA) is developing the township.