Township Progress
New Shillong's Administrative City Moves Closer to Use, with Secretariat Shift Eyed for Late 2027
Chief Minister Conrad K. Sangma said on 4 November 2026 that the Administrative City in New Shillong is coming up quickly and projected that the Secretariat will move there between September and November 2027. For Shillong, that means the old city's office crowding could ease, while the township's land, roads and jobs plan moves into its next stage.

| Statement date | Wednesday, 4 November 2026 |
|---|---|
| Secretariat move projected | September to November 2027 (CM's projection) |
| Secretariat complex cost | Rs 1,188 crore on a 53-acre site at Umsawli |
| Secretariat completion target | Mid-2027 (earlier reports; 35% complete as of February 2026) |
| Land acquired for township | Over 915 acres, acquired 1995 to 2017 (per CM, July 2026) |
| Total investment sanctioned | Over Rs 6,000 crore (as of March 2026) |
| Projected jobs | 1.5 lakh, long-term target across four sectors |
| Development authority | New Shillong Development Authority, from the Cabinet decision of 27 July 2026 |
What the Chief Minister said
On Wednesday, 4 November 2026, Chief Minister Conrad K. Sangma said the new Administrative City in New Shillong is coming up quickly. He made the remarks at the opening of two multilevel car parks in central Shillong, in the presence of Deputy Chief Minister Sniawbhalang Dhar. He projected that the Secretariat will shift to the Administrative City around September to November 2027, and said the move would significantly ease congestion in the old city.
Reports of the same remarks differ slightly on timing. One account gives the September to November 2027 window, while another says the majority of the Secretariat is expected to move toward the end of next year. Both point to late 2027, and the Chief Minister's own window is September to November.
The Secretariat complex at Umsawli
The Secretariat complex under construction at Umsawli, New Shillong, is costed at Rs 1,188 crore on a 53-acre site. The foundation stone was laid on 21 January 2025. Phase 1 of the complex covers 68 offices, a 700-person auditorium and facilities for 1,829 staff. Phase 2 adds 1.25 lakh square metres of floor area, 56 directorates, 4,746 staff capacity and two 200-seat auditoriums.
Earlier reporting put completion at mid-2027, and progress stood at 35% as of February 2026. The projected move window falls just after that target, so the shift depends on the building being finished and fitted out in time.
The car parks are in Shillong city, not the township
The two car parks opened on Wednesday sit inside Shillong city, not inside the township. The District School Education Office-cum-Multilevel Car Park at Mawkhar and the fully mechanised Multilevel Car Park at Motphran together hold 200 vehicles. They cost Rs 38.92 crore under the Shillong Smart City Mission and were built by Shillong Smart City Limited on a DBOMT model.
Shillong Smart City's CEO, Saloni Verma, had earlier said eight multilevel car parks with about 1,000 vehicles of combined capacity had been commissioned across Shillong. The Chief Minister also said about Rs 60 crore has been allotted to repair and beautify roads and railings across Shillong. These works serve the old city. They are separate from the township build-out.
What it means for land, roads and jobs
- Land: Over 915 acres were acquired between 1995 and 2017. In January 2024, 229.724 acres at Mawdiangdiang were allotted to the Urban Affairs Department for an Administrative Complex, and 807.7 acres at Mawkhanu were set aside for the Knowledge City.
- Investment: Total investment sanctioned is over Rs 6,000 crore as of March 2026. In July 2026 the Chief Minister said about 30% had already been used on infrastructure and key facilities.
- Roads: Central road funding of Rs 146.79 crore under PM-DevINE was reported in January 2024 for township roads.
- Jobs: The state's long-term target is 1.5 lakh jobs across tourism, sports and culture, education and skilling, and technology. Shillong Tech Park-II at Umsawli, with 1.8 lakh square feet of space built at Rs 121 crore, was inaugurated in late September 2026 and was reported nearly fully booked within two days.
- Governance: On 27 July 2026 the Cabinet converted the township agency into the New Shillong Development Authority, which has wider powers over urban planning, infrastructure and governance.
What comes next
Three markers will show whether the timeline holds. The first is the Secretariat's completion, targeted for mid-2027, followed by the September to November 2027 move window. The second is the new Assembly building at Mawdiangdiang, which the Speaker said on 13 October 2026 should be completed within 2026 without a cost increase, with a safety audit running alongside the work. The third is the Knowledge City at Mawkhanu, which was under development as of early 2026.
Construction in the hills is also limited by weather. The state's working window is about six to seven months because of heavy rain, and a July 2026 review linked the few delays it found to that window. Heavy rain in the coming monsoon will test the schedule again.
Development phases
Frequently asked questions
Is the Administrative City the same as the Secretariat complex at Umsawli?
The Chief Minister tied the Secretariat's move to the Administrative City. The Secretariat complex at Umsawli is the building under construction at Rs 1,188 crore, with completion targeted for mid-2027.
When is the Secretariat expected to move to New Shillong?
The Chief Minister projected a move between September and November 2027. One report of his remarks gave the timing as toward the end of 2027.
Are the new car parks inside New Shillong Township?
No. The two multilevel car parks at Mawkhar and Motphran are inside Shillong city. They hold 200 vehicles and were built under the Shillong Smart City Mission at Rs 38.92 crore.
Who now runs the New Shillong project?
Since the Cabinet decision of 27 July 2026, the township body has been the New Shillong Development Authority, which replaced the earlier township development agency.
How much land has been acquired for New Shillong?
The Chief Minister said over 915 acres were acquired between 1995 and 2017. Separately, 807.7 acres at Mawkhanu were set aside for the Knowledge City.
How many jobs is the township expected to create?
The state's long-term target is 1.5 lakh jobs across tourism, sports and culture, education and skilling, and technology.
Sources
- Shillong gets 200 new parking slots as city shifts from banning to building
- Shillong's parking pain gets some relief: CM opens two automated car parks
- Meghalaya Cabinet upgrades New Shillong Township body into powerful development authority, The Sentinel (28 July 2026)
- Tech Park nears full occupancy within two days of inauguration, The Shillong Times (26 September 2026)
- Corrections underway in new Assembly building after IIT-G flags minor issues, The Meghalayan Express (13 October 2026)
- New Shillong City to generate over 1.5 lakh jobs, says Meghalaya CM
- New Shillong still in devp stage despite crores spent, The Shillong Times (4 October 2024)
- 229 acres of land allotted for setting up of Administrative Complex, Highland Post
- New Shillong, Wikipedia