New Shillong Township's Command Centre Works, but Finished Shillong Projects Sit Unused
A November 2026 review of Shillong Smart City Mission projects finds the Integrated Command and Control Centre at New Shillong Township working well, while the Polo Commercial Complex, the Police Bazar Business-cum-Tourism Centre and the Laitumkhrah Municipal Market remain completed but not operational. For a township meant to take pressure off Shillong and create 1.5 lakh jobs, the gap between finished buildings and open services matters for land, roads and homes.

| Report date | 15 November 2026 |
|---|---|
| Working well | Integrated Command and Control Centre at New Shillong Township (Umsawli), as reported in November 2026 |
| Completed but not operational | Polo Commercial Complex; Police Bazar Business-cum-Tourism Centre; Laitumkhrah Municipal Market Phase I (as of November 2026) |
| Cancelled | Proposed six-kilometre Smart Road, dropped after work had started because the government found it unfeasible |
| Township land acquired | Over 915 acres, acquired 1995 to 2017 (as stated in the Assembly, July 2026) |
| Total investment sanctioned | Over Rs 6,000 crore (as of March 2026) |
| Projected jobs | 1.5 lakh, long-term target across tourism, sports and culture, education and skilling, and technology |
| Implementing agency | New Shillong Township Development Authority, with the Shillong Smart City Mission running the Smart City projects |
What the review found
A Shillong Smart City Mission review published on 15 November 2026 looked at projects that are finished but still not open to the public. The one item it describes as working well is the Integrated Command and Control Centre at New Shillong Township. Official reporting from November 2024 recorded Chief Minister Conrad K. Sangma inaugurating the centre at Umsawli, New Shillong.
The review also notes that multi-level parking facilities at a couple of city locations are operational. On 4 November 2026, the Chief Minister opened two car parks in Shillong: a district school education office-cum-multilevel car park at Mawkhar and a fully mechanised multilevel car park at Motphran. Together they hold 200 vehicles. The two car parks cost Rs 38.92 crore under the Mission and were built by Shillong Smart City Limited on a DBOMT model.
Finished projects still waiting to open
The review flags three completed projects that are not yet operational as of November 2026:
- Polo Commercial Complex. It was inaugurated by Union Finance Minister Nirmala Sitharaman and is about a year old, but it is still non-functional.
- Police Bazar Business-cum-Tourism Centre. The building is complete but not yet operational. The government has floated tenders to make it functional.
- Laitumkhrah Municipal Market. Phase I of the redevelopment is complete but not opened. Phase II is expected to be finished by the end of 2026.
For residents and traders, a finished building that stays shut adds no shops, offices or services. For buyers, it means the commercial demand that a Smart City project is meant to create is still waiting.
The cancelled Smart Road
The proposed six-kilometre Smart Road was cancelled after work had started. The government found the project unfeasible. For a township that depends on roads to link its administrative, education and tech zones with Shillong, the drop removes one planned corridor from the Mission's list. Road access to New Shillong is still covered by other route plans, including the Shillong-Umroi airport road and the four-lane extension from Umiam to Shillong.
What this means for New Shillong's growth
New Shillong Township is being built as the state's administrative, knowledge and institutional centre next to Shillong. Its growth depends on land, roads, utilities and jobs arriving in step. The command centre working is a useful sign that the township's control systems are running. The idle buildings in the city show that finishing a project is not the same as giving people a working service.
- Land: Over 915 acres were acquired between 1995 and 2017, and the Knowledge City at Mawkhanu has a further 807.7 acres.
- Roads and utilities: Works in the township include roads, water and power. The water supply plan covers 32 villages.
- Jobs: The long-term target is 1.5 lakh jobs. Shillong Tech Park II at Umsawli, which added 1.8 lakh sq ft of space in September 2026, is one early step toward that goal.
- Homes: Shillong's population has passed five lakh, which is the pressure the township was planned to ease.
What comes next
The review does not set a new deadline for the command centre, which is already in use. The timelines to watch are these:
- Laitumkhrah Municipal Market Phase II: expected to be completed by the end of 2026.
- Police Bazar Business-cum-Tourism Centre: tenders are out to make it operational.
- New Meghalaya Secretariat at Umsawli: Rs 1,188 crore on a 53-acre site, with completion targeted for mid-2027. The Chief Minister has projected the Secretariat will move into the Administrative City between September and November 2027.
For buyers and investors in Shillong and New Shillong, the practical test in the coming months is whether finished Smart City buildings open and start serving people. That will say more about the city's growth than any single announcement.
Frequently asked questions
Is the Integrated Command and Control Centre at New Shillong Township working?
The November 2026 review describes the Integrated Command and Control Centre at New Shillong Township as functioning well. It was inaugurated by Chief Minister Conrad K. Sangma at Umsawli, New Shillong.
Which Shillong Smart City projects are finished but not open?
As of November 2026, the Polo Commercial Complex, the Police Bazar Business-cum-Tourism Centre and Phase I of the Laitumkhrah Municipal Market are completed but not operational.
Has the Smart Road project been cancelled?
Yes. The proposed six-kilometre Smart Road was cancelled after work had started, because the government found the project unfeasible.
When will the new Secretariat move to New Shillong?
The Chief Minister has projected that the Secretariat will move to the Administrative City at Umsawli between September and November 2027, with completion of the complex targeted for mid-2027.
How much has been invested in New Shillong Township?
Over Rs 6,000 crore has been sanctioned for New Shillong Township as of March 2026, and over 915 acres were acquired between 1995 and 2017.
Sources
- Smart City projects ready but several remain unused, The Shillong Times (15 November 2026)
- Shillong Integrated Command and Control Centre inauguration, All India Radio North East (November 2024)
- Shillong's parking pain gets some relief: CM opens two automated car parks, Highland Post
- Shillong gets 200 new parking slots as city shifts from banning to building, The Meghalayan Express
- Tech Park nears full occupancy within two days of inauguration, The Shillong Times (26 September 2026)
- New Shillong