Project Oversight Update
NCLT-appointed panel flags construction delays and funding gaps at Jaypee Infratech under Suraksha Group
A committee appointed by the National Company Law Tribunal (NCLT) has reported delays and funding gaps at Jaypee Infratech's Wish Town project in Noida, which Suraksha Group controls. Its report, dated 20 August 2026, questions the developer's claim that 84 of 159 towers are complete and casts doubt on the September 2028 completion target. Note: City of the Ganges is a separate Suraksha township and is not the subject of this report.

| Report date | 20 August 2026 (status as of October 2026) |
|---|---|
| Who reported | Two-member NCLT-appointed committee, made up of former NCLT members Prasanta Kumar Mohanty and Deepti Mukesh; appointed February 2026 |
| Developer's claimed progress | 84 of 159 towers complete, 7,913 units; occupancy certificates for 42 towers (4,213 units), per a 30 July 2026 press conference |
| Labour requirement | 12,000 workers committed under the resolution plan; the panel found site presence consistently below this |
| Committed funding | About ₹3,000 crore to finish remaining units; the panel reportedly found a ₹3,000 crore credit facility due within 90 days was not arranged (allegation, not an adjudicated finding) |
| Completion target | September 2028 for Jaypee Wish Town (per the 2026 reporting); a March 2028 target for about 20,000 homes is also reported. The two dates have not been reconciled in the sources reviewed |
| State government review | Five-member Uttar Pradesh committee constituted 11 September, headed by Santosh Kumar, OSD, Noida Authority; Noida Authority CEO said it would report within a month |
| Developer control | Suraksha Group took over Jaypee Infratech in June 2024, after NCLT approved its bid in March 2023 and NCLAT upheld it in May 2024 |
What the panel reported
The NCLT-appointed committee said the Jaypee Infratech project shows significant delays and funding gaps. Its report, dated 20 August 2026, found major differences between the progress Suraksha Group has claimed and what was seen on site. The panel's concerns centre on the pace of construction and on transparency, and they raise doubts about the 2028 completion target.
The committee's mandate came from the tribunal's February 2026 order, which followed homebuyer applications and affidavits about long delays under the resolution plan approved in 2023.
The developer's numbers and the gap
Suraksha Group has said that 84 of the 159 towers at Wish Town are complete and that 42 of them have occupancy certificates. A company official put the completed units at 7,913, with occupancy certificates covering 4,213 flats. Applications for another 28 towers covering 2,385 flats had been submitted, according to that official.
The panel did not accept the picture at face value. It pointed to insufficient labour as the main reason for slow progress and questioned whether the reported use of premium-grade building materials matched what inspectors found on site.
Arithmetic from the reported figures: 84 towers is about 53% of 159, and 42 towers with occupancy certificates is about 26%. These percentages are our calculation from the reported counts, not figures published by the developer or the panel.
Labour, materials and money
The resolution plan required Suraksha Group to keep 12,000 workers on site. The panel found actual presence consistently below that level. Reporting on the same findings also says site inspections noted labour shortages and the replacement of premium steel brands with lower-grade alternatives. These are allegations drawn from the committee's findings as reported by the press, and they have not been tested in a court.
On money, the reports say the ₹3,000 crore facility the plan required was not put in place within the 90-day window. They also allege that funds meant for completion were moved into mutual funds and associate entities. A separate police investigation into alleged misuse of homebuyer funds is also reported as pending.
Who is deciding
The NCLT is the body that approved Suraksha Group's resolution plan and appointed the committee. The Uttar Pradesh government has separately formed a five-member committee to examine construction progress, compliance with approved layouts, and whether buyer money is being used for construction. It includes officials from the planning and finance departments of the Noida and Yamuna authorities.
Suraksha Group has said that it is progressing with the project according to the approved resolution plan. The company has not, in the sources reviewed, accepted the panel's specific findings.
What it changes for buyers
For homebuyers, the gap between completed towers and towers with occupancy certificates matters most. Buyers can move in only once an occupancy certificate is issued, so the 42 certified towers are the figure that matters for possession. Buyers have also reported non-functional lifts, incomplete fire-safety systems, and unfinished water, sewage, roads and clubhouses in some towers.
Nothing in the reporting reviewed says the resolution plan has been cancelled or that the 2028 target has been formally revised by a court or regulator.
What is next
Three processes are open. First, the NCLT committee's report is before the tribunal, which will decide what follows. Second, the Uttar Pradesh committee was expected to report within about a month of its formation. I did not find its outcome in the sources reviewed. Third, Suraksha Group has to show that its funding and labour commitments are being met.
Buyers should check the status of their own tower against the occupancy certificate records and the latest project notices from Jaypee Infratech.
Context: where City of the Ganges fits
Suraksha Group has also outlined three townships across 465 acres: City of the Ganges, Enterprise City and Yamuna Smart City. The August 2026 committee report and the Wish Town dispute do not cover City of the Ganges. This article therefore makes no claim about that township's status.
Frequently asked questions
Who appointed the committee that issued the August 2026 report?
The National Company Law Tribunal appointed a two-member committee in February 2026. Its members are former NCLT members Prasanta Kumar Mohanty and Deepti Mukesh. The report is dated 20 August 2026.
What is the main dispute?
The committee questioned Suraksha Group's claim that 84 of 159 towers are complete. It cited labour shortfalls and concerns about construction materials, and it said progress and transparency do not match what it found on site.
Has Suraksha Group responded?
Suraksha Group has said it is progressing with the project according to the approved resolution plan. I did not find a detailed rebuttal of the committee's specific findings in the sources reviewed.
Is the September 2028 deadline still in place?
Reporting from 2026 cites September 2028 as the completion target for Jaypee Wish Town. Other reporting cites March 2028 for about 20,000 homes. I could not reconcile the two dates from the sources reviewed, and no formal revision was found.
Does this affect City of the Ganges?
The reports reviewed concern Jaypee Wish Town in Noida. They do not mention City of the Ganges, so this article does not assess that township.
What happens next?
The NCLT will consider the committee's report. The Uttar Pradesh committee formed on 11 September was expected to report within about a month, and I did not find its outcome in the sources reviewed.
Sources
- Jaypee Infratech Resolution Faces NCLT Committee Scrutiny (Whalesbook)
- Panel Flags Construction Delays at Jaypee Infratech (Whalesbook)
- Suraksha Group Alleged to Breach Jaypee Infratech Resolution Plan (Whalesbook)
- Jaypee homebuyers still wait as NCLT flags problems with the revival plan (Inventiva)
- Jaypee's Wish Town: A Wish Granted, But Not The Homes (Inventiva)
- UP Government Panel Begins Probe Into Jaypee Wish Town Construction Delays (H4E News)
- Jaypee Wish Town buyers flag possession delays despite occupancy certificates (PropNewsTime)
- Suraksha Group expects to complete 20,000 Jaypee homes by '28 (Construction Week India)
- Suraksha Group to Spend ₹3,000 Cr to Finish Jaypee Infratech Projects by 2028 (Whalesbook)
- Suraksha Group Targets March 2028 to Complete Jaypee Infratech Homes (Whalesbook)
- Jaypee Infratech to invest Rs 6,000 cr to finish 20,000 homes in 3 years (Business Standard/PTI)
- NCLT Steps In: Jaypee Infratech Project Delays Under Scrutiny (Whalesbook)