New Cities India

Planning Decision

BIDA Master Plan 2045 Receives Board Approval

By October 2025, the board of the Bundelkhand Industrial Development Authority (BIDA) had approved the Master Plan 2045, the statutory land-use plan for a 253.33 sq km greenfield industrial city across 33 villages in Jhansi tehsil, with detailed sector and zonal planning continuing afterward.

Bundelkhand Industrial Development Authority (BIDA) Greenfield City — BIDA Master Plan 2045 Receives Board Approval
Approving bodyBIDA Board (Bundelkhand Industrial Development Authority, Govt. of Uttar Pradesh)
Status as ofOctober 2025 — board-approved; sector/zonal planning ongoing
Plan area253.33 sq km (62,599.20 acres) across 33 revenue villages, Jhansi tehsil
Plan authorsConsortium led by Surbana Jurong (Singapore) with CBRE
Draft plan public notice11 April 2025 (draft Building Regulations 2045: 26 April 2025)
Industrial land share35.8% of planned area
Residential land share15.2% of planned area
Green space share10.6% of planned area
Distinct land-acquisition target56,662 acres approved for phased acquisition (separate from the 62,599-acre plan area)

What was decided

The decision recorded here is the BIDA board's formal approval of the Master Plan 2045 — the long-term land-use and zoning framework for BIDA's notified planning area. By October 2025, the master plan had received BIDA board approval, while sector and zonal planning continued. This approval is a planning-authority decision, not a construction or completion milestone: it fixes the broad allocation of land to different uses across the plan area and clears the way for detailed sector layouts, building regulations and environmental clearance to proceed.

The body and its mandate

BIDA is a statutory industrial development and planning authority of the Government of Uttar Pradesh, headquartered in Jhansi, constituted under the Uttar Pradesh Industrial Area Development Act, 1976 to plan, develop and regulate an integrated industrial and urban township in the Bundelkhand region. The BIDA Master Plan 2045 covers 253.33 km2 (97.81 sq mi), equivalent to 62,599.20 acres, across 33 villages in Jhansi tehsil.

This total planning area is distinct from the 56,662 acres approved for phased land acquisition and development. In other words, the master plan sets out land-use zoning for the whole notified area, while a separate, smaller acreage figure covers land the state is actually acquiring in phases for direct development.

Path to board approval

Operative land-use allocation

Under the BIDA Master Plan 2045, 253 sq km of land has been designated for specific uses: Industrial (35.8 per cent), residential (15.2 per cent), mixed-use (5.1 per cent), commercial (1.5 per cent), and green space (10.6 per cent). The remaining share is allocated to institutional, logistics, infrastructure and other uses not broken out in the percentages reported so far. The planned city combines industrial, residential, commercial, institutional, logistics and green uses.

Connectivity and sector directives tied to the approval

Following the board approval, the state government layered in connectivity directives. Chief Minister Yogi Adityanath issued directives for the construction of an airport and improved connectivity in the BIDA region, emphasising the extension of the Agra-Gwalior Expressway, the Delhi-Chennai railway line, a multimodal logistics park, and a link expressway from the Bundelkhand Expressway. Sector planning work was expected to conclude by November 30, 2025, while the Environmental Impact Assessment process was progressing. Connectivity projects linking BIDA to NH-27 and NH-44 were in their final stages, and plans were underway for a railway station, logistics park, IT park, truck terminal, and bus depot within the area.

How this differs from the land-acquisition programme

The master-plan approval should not be confused with land-acquisition announcements, which cover a smaller, phased acreage inside the wider plan area. In February 2026, the state government was reported to have formally approved 56,662 acres for phased acquisition and development, including a first-phase target of 35,298 acres and a second-phase target of 21,364 acres. About 22,000 acres, or nearly 40 per cent of the identified swathes, had been acquired by BIDA as of early November 2025, according to a senior official. By March 2026, the acquisition of 24,201 acres amounted to more than 68 per cent of the total 35,298 acres targeted in the first phase.

Practical effect for landowners, investors and industry

For landowners in the 33 notified villages, board approval of the master plan confirms which broad zone (industrial, residential, commercial, mixed-use or green) their land falls into, which in turn affects acquisition priority and compensation planning. To ensure transparency, BIDA introduced a digital software system that oversees every stage of land acquisition — from farmer consent to payment — and a dedicated call centre for farmers.

For investors, the approval signals that BIDA can proceed to detailed sector plans and building regulations, and start commissioning trunk infrastructure. BIDA issued a Request for Proposal in April 2025 to select a consultant for technical and financial feasibility assessments and detailed project reports for infrastructure components planned within the Activation Area of its Master Plan 2045. The Activation Area forms the first phase of a multi-phase development under the Master Plan 2045. By June 2026, BIDA's CEO said that approximately 2,500 acres around Dagarwaha, Rajapur and Bamer villages would form this first activation area, combining industrial plots with housing, education and other civic facilities.

Subsequent regulatory steps

Board approval of the master plan was followed by continued environmental appraisal for the underlying Greenfield Industrial City project. The environmental appraisal process included an Expert Appraisal Committee review in June 2025, a public hearing in Jhansi on 22 December 2025 and further committee reviews in March and April 2026, with environmental clearance reported in June 2026. The Ministry of Environment, Forest and Climate Change subsequently granted environmental clearance to the 'Greenfield Industrial City (BIDA Master Plan-2045)' project, covering an area of 253.33 square kilometres across 33 rural areas of Jhansi tehsil.

Development phases

Phase 1 (land acquisition)target by March 2026 per official directive35,298 acres targeted; 24,201 acres (68%+) acquired asof March 2026Phase 2 (land acquisition)following Phase 121,364 acres targetedActivation Area (first development zone)in progress, as of June 2026~2,500 acres around Dagarwaha, Rajapur and Bamervillages

Land use

Industrial35.8%Residential15.2%Green space10.6%Mixed-use5.1%Commercial1.5%

Frequently asked questions

What exactly was approved in October 2025?

The BIDA board approved the Master Plan 2045 — the land-use and zoning blueprint for the authority's 253.33 sq km notified planning area. Sector-level and zonal planning continued after this approval.

Who prepared the Master Plan 2045?

A consortium led by Singapore-based Surbana Jurong, together with real-estate consultancy CBRE, was selected to prepare the plan after BIDA invited bids in January 2024.

Does board approval mean construction has started?

No. Board approval of the master plan is a planning decision fixing land-use zones. Physical development depends on separate steps such as land acquisition, environmental clearance, and detailed project reports for specific infrastructure and 'activation area' components.

How is the 253 sq km plan area different from the 56,662-acre acquisition figure?

The 253.33 sq km (about 62,599 acres) is the full notified planning area covered by the Master Plan 2045. The 56,662 acres is a separate, phased target for land the state is actually acquiring for direct development within that wider area.

What share of land is set aside for industry versus housing?

Under the approved plan, 35.8% of the area is designated industrial, 15.2% residential, 10.6% green space, 5.1% mixed-use and 1.5% commercial.

What comes after the master plan approval?

Following board approval, BIDA proceeded with sector and zonal planning, draft Building Regulations 2045, environmental appraisal (leading to environmental clearance), and detailed project reports for an initial 'Activation Area' of about 2,500 acres.

Sources

Interested in Bundelkhand Industrial Development Authority (BIDA) Greenfield City?

Register once — get informed when projects, plot schemes or launches open up here.