New Cities India

Master Plan Explainer

BIDA Master Plan 2045: Bundelkhand Greenfield Industrial City Planning Blueprint

The Bundelkhand Industrial Development Authority (BIDA) is building a new industrial city near Jhansi under a plan that runs to 2045, with a total notified planning area far larger than the land currently being acquired and developed.

Bundelkhand Industrial Development Authority (BIDA) Greenfield City — BIDA Master Plan 2045: Bundelkhand Greenfield Industrial City Planning Blueprint
Planning horizonMaster Plan 2045 (20-year horizon)
Total notified planning area253.33 km² / 62,599.20 acres across 33 villages, Jhansi tehsil
Land approved for phased acquisition & development56,662 acres (distinct from the full planning area)
First activation phase~2,500 acres near Dagarwaha, Rajapur and Bamer villages
Planner/consultantSurbana Jurong (Singapore)-led consortium with CBRE
Draft plan released for public objections11 April 2025
Board approval of master planBy October 2025
Environmental clearance (MoEFCC)Granted, reported June 2026

What BIDA is and the planning horizon

The Bundelkhand Industrial Development Authority (BIDA) is a statutory industrial development and planning authority of the Government of Uttar Pradesh, headquartered in Jhansi, constituted under the Uttar Pradesh Industrial Area Development Act, 1976 to plan, develop and regulate an integrated industrial and urban township in the Bundelkhand region. The authority's guiding document, the BIDA Master Plan 2045, sets a roughly 20-year planning horizon from its preparation to the year 2045. The Uttar Pradesh cabinet approved the proposal to establish BIDA in 2023, and the Governor of Uttar Pradesh formally notified the BIDA area on 14 September 2023. The authority held its first board meeting on 4 January 2024 and its second on 28 June 2024.

Total planned area vs. area targeted for development

It is important to distinguish two different numbers that both appear in official material and news coverage:

As of the most recent reporting, acquisition is well underway but incomplete. The acquisition of 24,201 acres of land amounts to more than 68 per cent of the total 35,298 acres targeted in the first phase by BIDA. A separate, more recent figure tied to the environmental clearance announcement put the cumulative total higher: BIDA has so far acquired a total of 25,706 acres of land (as of the June 2026 clearance report). Authorities have also approved further tranches beyond the original 56,662-acre figure — a total of 8,349 acres of land will be acquired for the Bundelkhand Industrial Development Authority's Master Plan-2045, alongside an extension of the Agra-Gwalior Greenfield Expressway to Jhansi, agreed at a Project Monitoring Group meeting chaired by the Chief Secretary in December 2025.

Land-use split (Master Plan 2045)

Under the BIDA Master Plan 2045, 253 sq km of land has been designated for specific uses: Industrial (35.8 per cent), residential (15.2 per cent), mixed-use (5.1 per cent), commercial (1.5 per cent), and green space (10.6 per cent). These five categories together account for about 68 percent of the notified area; the remaining share (institutional, infrastructure, roads, water bodies and similar uses) has not been broken out in public reporting as of this writing, so no figure is given here to avoid guessing.

Development phases and timeline

BIDA's rollout has three broad, overlapping layers — land acquisition phases, a first construction/activation phase, and the regulatory approval sequence for the plan itself.

Land acquisition phases

First construction phase — the "Activation Area"

The Activation Area forms the first phase of a multi-phase development under the BIDA Master Plan 2045, which envisions a self-sustaining industrial city in the Bundelkhand region. In June 2026, CEO Sanjay Kumar Khatri said that approximately 2,500 acres around Dagarwaha, Rajapur and Bamer villages would form the first activation area, combining industrial plots with housing, education and other facilities. BIDA has commissioned a consultant to prepare feasibility studies and detailed project reports for the Activation Area's infrastructure, spanning 12 segments including a 38-kilometre greenfield expressway, power transmission, water supply, sewage treatment, and ICT systems.

Plan approval sequence

The Ministry of Environment, Forest and Climate Change officially granted environmental clearance to the 'Greenfield Industrial City (BIDA Master Plan-2045)' project, to be developed over 253.33 square kilometres covering 33 rural areas of Jhansi tehsil.

Utilities planned alongside the city

The environmental clearance documentation sets out specific utility capacities tied to the plan: the city's drinking water requirement of 217.22 MLD will be met from Rajghat Dam, while treated water will be used for other purposes. BIDA will establish a 163.26 MLD Sewage Treatment Plant and a 150.88 MLD Common Effluent Treatment Plant in phases. Used water will be treated and reused, and no wastewater of any kind will be discharged into the Betwa, Pahuj or Angauri rivers.

Population and employment targets

BIDA and its consultants have not published a specific population or workforce target figure in the material reviewed for this page (as of August 2026). What is documented is the intent: BIDA will be developed as one of the country's most modern, sustainable and environment-friendly industrial smart cities, according to CEO Sanjay Kumar Khatri, with the stated aim of improving local living standards alongside industrial growth. Readers should treat any population or jobs numbers circulating in secondary sources with caution until BIDA publishes them in the approved Master Plan 2045 document itself; this page will be updated when official figures are confirmed.

Planner and regional context

A consortium led by Singapore-based Surbana Jurong and real-estate consultancy CBRE was selected to prepare the plan. The project sits within two larger national industrial-corridor programmes: Jhansi is one of the six nodes of the UP Defence Industrial Corridor (UPDIC), alongside Lucknow, Kanpur, Agra, Aligarh, and Chitrakoot, and Chief Minister Yogi Adityanath has also called for the development of a Delhi–Nagpur Industrial Corridor node in the BIDA region to align with the national industrial map. The initial programme included a ₹5,000 crore land-purchase fund and was widely described as a Noida-like industrial-city project intended to accelerate industrialisation in Bundelkhand.

Where to find the official plan documents

Official notices, RFPs and plan-related documents are published on BIDA's own website. The consultant-selection RFP for the Vision Document and Master Plan 2045 is one such document; broader tender and notice listings covering later stages (including the Activation Area infrastructure DPR consultancy) are maintained on the same site. For the underlying government approval trail — including the environmental clearance — the Ministry of Environment, Forest and Climate Change's Parivesh portal is the relevant record-keeper. This page links to these sources rather than reproducing their content; consult them directly for the full plan text, drawings and regulations.

Development phases

Acquisition Phase Iongoing, target ~68%+ acquired by early 202635,298 acres target; 24,201 acres(68%+) acquired as of reportingAcquisition Phase IIpending21,364 acres remaining to reach the56,662-acre totalAdditional acquisition trancheapproved December 20258,349 acres, alongside Agra–GwaliorExpressway extension to JhansiActivation Area (firstconstructionDPRs tendered 2025; development to follow~2,500 acres near Dagarwaha, Rajapurand Bamer villages

Land use

Industrial35.8%Residential15.2%Green space10.6%Mixed-use5.1%Commercial1.5%

Frequently asked questions

What is the planning horizon of the BIDA Master Plan?

The plan is named Master Plan 2045, giving it a roughly 20-year horizon from its preparation period to 2045.

How big is the BIDA project area, and is all of it being developed now?

No. The notified planning area covers 253.33 km² (62,599.20 acres) across 33 villages in Jhansi tehsil, but only 56,662 acres have been approved for phased acquisition and development so far — a smaller subset of the full planning area.

What share of land is set aside for industry versus housing?

Under the Master Plan 2045, industrial use accounts for 35.8%, residential for 15.2%, green space 10.6%, mixed-use 5.1% and commercial 1.5% of the designated 253 sq km area; the remaining share covering other uses has not been separately detailed in public reporting.

Who prepared the BIDA Master Plan 2045?

A consortium led by Singapore-based Surbana Jurong, together with real-estate consultancy CBRE, was selected by BIDA to prepare the vision document and Master Plan 2045.

What is the 'Activation Area'?

It is the first construction/development phase under the master plan — roughly 2,500 acres around Dagarwaha, Rajapur and Bamer villages, combining industrial plots with housing and education facilities, for which infrastructure feasibility studies and detailed project reports were commissioned in 2025.

Has the master plan been formally approved?

The draft plan was released for public objections in April 2025, received BIDA board approval by October 2025, and the associated Greenfield Industrial City project received environmental clearance from the Union Ministry of Environment, Forest and Climate Change, reported in June 2026.

Are population or employment targets published?

Not in the sources reviewed as of August 2026. BIDA has stated an intent to build a modern, sustainable industrial smart city, but has not released specific population or jobs figures publicly; this page will be updated once official numbers are confirmed.

Sources

Interested in Bundelkhand Industrial Development Authority (BIDA) Greenfield City?

Register once — get informed when projects, plot schemes or launches open up here.