BMRDA Decision Record
Bidadi Integrated Township and Satellite Town Ring Road Approved by BMRDA
The Bidadi integrated township, also searched as GBIT or Bidadi Township, and the Satellite Town Ring Road (STRR) were formally approved at a BMRDA meeting chaired by Chief Minister Siddaramaiah. The township is planned in Ramanagaram district near Bengaluru, and as of 11 November 2026 its status is Upcoming, with no BHK types or prices announced.

| Decision | Formal approval of the Bidadi integrated township and the Satellite Town Ring Road (STRR) |
|---|---|
| Decision body | BMRDA meeting chaired by Chief Minister Siddaramaiah |
| Reported on | 11 November 2026 |
| Planning role | BMRDA is the special purpose vehicle and local planning authority for both projects |
| Township area | About 9,178.29 acres in 10 villages of Ramanagaram district |
| Legal framework | Development Plan and Town Planning Scheme under the Town and Country Planning Act, 1961 |
| Status (as of 11 November 2026) | Upcoming |
| BHK types and prices (as of 11 November 2026) | Not yet announced |
What the BMRDA approval covers
The Bidadi integrated township and the Satellite Town Ring Road were formally approved at a BMRDA meeting chaired by Chief Minister Siddaramaiah. The approval names BMRDA as the special purpose vehicle and local planning authority for both projects. Both are to be developed under a Development Plan and a Town Planning Scheme made under the Town and Country Planning Act, 1961.
The township is described in the approval report as covering about 9,178.29 acres across 10 villages of Ramanagaram district. It is about 25 km from Bengaluru and is designed as a work-live-play township with dedicated sectors for industries alongside homes and civic facilities.
This record covers the decision itself. Other milestones, including land notifications by the Greater Bengaluru Development Authority (GBDA), are set out further down the page.
Land split and villages
The approval report divides the township area into three categories of land, as shown below.
| Land category | Area |
|---|---|
| Water bodies | 643 acres |
| Private land | 6,336.33 acres |
| Government land | 2,198.21 acres |
A separate Regional Township Authority would cover 38 additional villages in three hoblis: Bidadi, Kailancha and Ramanagaram. Buyers should note that the area is reported differently across sources. The approval report cites about 9,178 acres in 10 villages, while the GBDA final notifications so far cover nine villages, with over 7,335 acres in final notices as of 2 November 2026.
How landowners would be compensated
The approval report proposes an Amaravati-style land model. Under it, landowners would receive developed land rather than only cash. The proposal sets out 1,000 sq yd residential plots and 200 to 300 sq yd commercial plots per acre for land within 5 km of the township, along with an annuity.
Landless families would receive a pension for 10 years under the same proposal. The proposal is a plan, and the final terms will depend on the scheme that is adopted.
Satellite Town Ring Road (STRR)
The STRR has a total length of 383 km, including 179 acres of radial roads. BMRDA also plans a separate 163 km Inter Town Ring Road. The STRR is planned for completion in three to five years.
For buyers, the ring road matters because it sets out the road links that would connect the township with the wider region. Its alignment and timing will affect travel times once it is built.
Where the township stands separately as of November 2026
The approval is one step in a longer process that runs alongside the GBDA-led project. The sequence of milestones so far is as follows.
- Cabinet approval of the original proposal came in January 2025.
- GBDA issued a preliminary land acquisition notification on 12 March 2025, which affected about 10,450 landowners.
- The Karnataka government granted approval for the current version of the project on 7 May 2026.
- The first final land notification, dated 13 June 2026, covered Kempayyanapalya, Vaderahalli and Mandalahalli, with about 499 to 518 acres depending on the report.
- A second final notification on 15 July 2026 covered over 4,941 acres in four villages.
- The final notifications issued on 2 November 2026 cover about 1,895 acres in Byramangala and Kanchugaranahalli, taking the total under final notices to over 7,335 acres.
Funding and cost figures are also reported. HUDCO has offered a loan of up to Rs 21,000 crore. Total project cost estimates vary from Rs 18,133 crore to about Rs 22,000 crore, depending on the report. GBDA has floated a Rs 26-crore tender for a 12-month consultancy covering the master plan and Detailed Project Report.
What this decision means for buyers
This approval confirms the planning route for the Bidadi township and the STRR. It does not mean homes, plots or commercial space are on sale. As of November 2026, no BHK types or prices have been announced, and the township has not been built.
Land acquisition is still under way. Some landowners and groups oppose the project. A #SaveBidadi campaign on social media started on 1 November 2026, citing ecological concerns, and an NGO has asked the National Green Tribunal to take suo motu cognisance. Buyers should watch the final master plan, the adopted development scheme and the official price and unit announcements before making any decision.
Frequently asked questions
What did BMRDA approve for Bidadi?
BMRDA formally approved the Bidadi integrated township and the Satellite Town Ring Road (STRR) at a meeting chaired by Chief Minister Siddaramaiah.
Who is the planning authority for the Bidadi township?
BMRDA is the special purpose vehicle and local planning authority for both the Bidadi township and the STRR.
How big is the Bidadi township?
The BMRDA approval report cites about 9,178.29 acres across 10 villages of Ramanagaram district, while the GBDA final notices so far cover nine villages.
Can I buy a plot or flat in the Bidadi township now?
No BHK types or prices have been announced as of 11 November 2026, and the township has not yet been built.
How long will the Satellite Town Ring Road take to build?
The STRR is planned for three to five years and has a total length of 383 km.
Sources
- Bidadi township, Satellite Town Ring Road approved by BMRDA (Deccan Herald)
- Karnataka government issues final notification to acquire land for Bidadi project (Deccan Herald, 2 Nov 2026)
- Karnataka issues final land acquisition notification for Greater Bengaluru township (The News Minute)
- Karnataka issues final gazette for Bidadi Township, farmers intensify land protest (NewsFirst)
- Final notification issued for Greater Bengaluru Integrated Township land acquisition near Bidadi (NammaAward)
- Bidadi Integrated Township gets boost with Rs 21,000-cr HUDCO loan offer (Deccan Herald)
- Govt begins land acquisition process to develop Bidadi township (Deccan Herald, March 2025)
- Greater Bengaluru Development Authority expands jurisdiction, takes over 22 more villages (Deccan Herald)
- Savebidadi campaign on November 1 to oppose township (Deccan Herald)
- Final notification for Bidadi township by June-end, Shivakumar defends project (Deccan Herald)
- Bidadi GBIT project, land acquisition process and compensation raises critical questions (Citizen Matters)