Land Acquisition Status
Greater Bengaluru Integrated Township (Bidadi): Land Acquisition
The Greater Bengaluru Integrated Township at Bidadi, near Bengaluru, is being assembled by the Greater Bengaluru Development Authority (GBDA). As of November 2026, reports say final acquisition notifications cover more than 7,335 acres in total, with compensation figures ranging from Rs 2.07 crore to above Rs 3 crore per acre.

| Developer / acquiring authority | Greater Bengaluru Development Authority (GBDA), set up in November 2023 to revive the Bidadi township (as of November 2026) |
|---|---|
| Acquisition route | Agreements with landowners under Section 35 of the Karnataka Urban Development Authorities Act, 1987; where no agreement is reached, Section 36 links acquisition to the LARR Act, 2013 (as of November 2026) |
| Final notifications issued | 518 acres in three villages (June 2026); 1,895 acres in two villages by a notification dated 30 October 2026; more than 7,335 acres in total across final notifications (as of November 2026) |
| Landowners named in latest notification | 3,271 (30 October 2026 notification) |
| Compensation rate | Minimum of Rs 2.07 crore per acre set by the Urban Development Department in June 2026; figures of Rs 2.14 crore and Rs 2.30 crore per acre were reported later in 2026; the Chief Minister has stated more than Rs 3 crore per acre (as of August 2026) |
| Estimated project cost | About Rs 20,000 crore (reported estimate); HUDCO has offered a loan of up to Rs 21,000 crore that GBDA will draw only as needed |
| Original preliminary notice | March 2025, covering about 7,481 acres across nine revenue villages (figures vary in reports) |
How the land is being acquired
The project is run by GBDA under the Karnataka Urban Development Authorities Act, 1987. Reporting describes two routes: negotiated agreements with landowners under Section 35, and, where no agreement is reached, acquisition under Section 36, which brings in the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
The first preliminary notice was issued in March 2025, after Cabinet approval in January 2025. It proposed taking about 7,481 acres across nine revenue villages. Other reports put the preliminary area at 7,418 or 9,600 acres, so the exact figure depends on the source.
The developed-land share has been described in two ways. In 2025, the GBDA Commissioner said landowners would receive 40% of developed land in return for giving up their rights. In 2026, reports described a 50:50 option, where landowners can choose half of the developed land instead of cash. Reports also describe annual annuities of Rs 30,000 to Rs 50,000 per acre, depending on land type, with Rs 25,000 a year for landless families, to bridge the years before developed plots are handed over.
A preliminary notification bars landowners in the area from new property transactions or changes to land use while acquisition is under way.
Compensation rates reported so far
| Rate or figure | Amount | Reported |
|---|---|---|
| Minimum for first-phase notified land | Rs 2.07 crore per acre | June 2026, Urban Development Department |
| Minimum payment in a later report | Rs 2.14 crore per acre | Mid-2026 |
| Land price fixed after first cheques | Rs 2.30 crore per acre, plus compensation for trees | Mid-2026 |
| Chief Minister's stated revised figure | More than Rs 3 crore per acre | August 2026 |
| Farmers' demand | Rs 5 to 6 crore per acre | 2026 |
The first cheques were reportedly handed to seven farmers from Kempaiahanapalya in June 2026. More than 200 landowners have applied for compensation, and the government has asked them to submit sale deeds, gift or partition deeds, and identity documents.
Villages covered
Ramanagara taluk (Bidadi hobli), first phase: Kempayyanapalya (384.22 acres), Mandalahalli (71.13 acres) and Vaderahalli (63.10 acres), together 518.45 acres, affecting around 754 farmers.
Bengaluru South district, latest notification: Kanchugaranahalli and Byramangala villages of Bidadi hobli, 1,895 acres, notified on 30 October 2026. Recent reporting places the township in Bengaluru South district, while earlier reports name Ramanagara district.
Other villages named in the township plan: Allalasandra, Gollarapalya, Bannigere, Hosur, Kanchugaranahalli Kaval and Mandlahalli are named among the villages in the project area.
Wider GBDA jurisdiction: A March 2026 order added 22 villages to GBDA limits: eight from Ramanagara taluk, six from Harohalli taluk and eight from Bengaluru South taluk. This brings GBDA's jurisdiction to 59 villages. These villages are under planning control, not all are under acquisition.
Farmer protests and disputes
Farmers have protested against the acquisition for more than 400 days, arguing that the land is productive, multi-cropped farmland. Farmers from around 26 villages have taken part in demonstrations. Around 60% of the affected landholders own half an acre or one acre.
The BJP held protests against the acquisition, and the JD(S) organised a padayatra from Bairamangala Circle in August 2026. In July 2026 the Chief Minister announced a committee to review the project. In a statement reported during the protests, the Chief Minister assured farmers that land would not be taken forcibly and that those unwilling to sell could continue farming. Farmers in the affected villages say they will keep opposing the acquisition.
Budget and funding
Reports give the township's estimated cost as nearly Rs 20,000 crore. A separate estimate puts land acquisition at about Rs 10,000 crore. HUDCO has offered a loan of up to Rs 21,000 crore to help fund land acquisition and civil works, and GBDA has said it will draw on the loan only as needed. These are estimates and an offer; they are not an approved allocation.
Current stage (as of November 2026)
The township is at the land acquisition stage. Final notifications have been issued in stages: 518 acres in June 2026, a further final notification for about 4,944 acres across four villages reported in July 2026, and 1,895 acres on 30 October 2026. Compensation payments have started in limited cases. Farmers in the notified villages continue to oppose the acquisition.
Planned land use
The original plan set aside 25% of the land for residential plots, 25% for economic activity, 25% for roads and utilities, 15% for parks and open spaces and 10% for civic amenities.
Frequently asked questions
Use the question headings below for quick answers.
Land use
Frequently asked questions
What compensation is being offered for land in the Bidadi township?
The Urban Development Department has fixed a minimum of Rs 2.07 crore per acre for notified land, and later reports cite Rs 2.14 crore and Rs 2.30 crore per acre. The Chief Minister has stated a figure above Rs 3 crore per acre (as of August 2026).
How many acres have been notified for acquisition so far?
Final notifications have covered 518 acres in three villages in June 2026 and 1,895 acres in two villages on 30 October 2026, with reports putting the total above 7,335 acres (as of November 2026).
Which villages are covered by the Bidadi township acquisition?
The first-phase villages are Kempayyanapalya, Mandalahalli and Vaderahalli, and the latest notification covers Kanchugaranahalli and Byramangala (as of November 2026).
Is the land being acquired by agreement or by award?
Acquisition is planned through agreements with landowners under Section 35 of the KUDA Act, and where no agreement is reached, Section 36 links it to the LARR Act, 2013 (as of November 2026).
Can landowners sell or change land inside the notified area?
Under the preliminary notification, landowners are barred from new property transactions or changes to land use during the acquisition process.
Sources
- Karnataka issues final land acquisition notification for 1,895 acres for Bidadi township - The News Minute
- 516 acres to be acquired for Bidadi township - The Hans India
- Bidadi Township: What the project is, who opposes it and why - The News Minute
- Bidadi AI township: Karnataka raises land compensation to over ₹3 crore an acre - The South First
- Farmers rally against Karnataka's Bidadi township project - The South First
- Karnataka issues final gazette for Bidadi Township, farmers intensify land protest - NewsFirst
- Notification for acquisition of 518 acres issued for Bidadi township project despite opposition from farmers - Public TV English
- Farmers fume as govt issues final notification on proposed Bidadi township project - Deccan Herald
- BJP holds protests against land acquisition for proposed Bidadi township project - ThePrint
- Bidadi GBIT project: Land acquisition process and compensation raises critical questions - Citizen Matters
- Govt begins land acquisition process to develop Bidadi township - Deccan Herald
- Greater Bengaluru Development Authority expands jurisdiction, takes over 22 more villages - Deccan Herald
- Bidadi Integrated Township gets boost with Rs 21,000-cr HUDCO loan offer - Deccan Herald
- Villages in Bidadi hobli oppose move to include them in Greater Bengaluru - Deccan Herald
- Farmers in Bidadi protest township plan - Deccan Herald
- Devanahalli redux: Farmers in Karnataka's Bidadi vow to fight AI city - Deccan Herald