Greater Bengaluru Integrated Township: Master Plan

The Greater Bengaluru Integrated Township (GBIT), also searched as Bidadi Township, Bidadi Integrated Township and Bidadi-Harohalli Township, is a planned mixed-use township at Bidadi in Karnataka, implemented by the Greater Bengaluru Development Authority (GBDA). A consultant tender has been floated, and final land acquisition notices cover over 7,335 acres.

Greater Bengaluru Integrated Township (Bidadi) — Greater Bengaluru Integrated Township: Master Plan
Implementing authorityGreater Bengaluru Development Authority (GBDA); BMRDA served as special purpose vehicle and local planning authority in the earlier plan
Proposed township area7,481 acres across nine villages (cabinet-approved revision, May 2026)
Final acquisition noticesOver 7,335 acres, as of November 2026
Planning horizon30 years, per the consultant's study scope (June 2026)
Total cost estimateRs 18,133 crore, government estimate as reported in June 2026
Land-use split (original plan)25% residential, 25% economic activity, 25% roads and utilities, 15% parks and open space, 10% civic amenity

Planning history and current stage

The township was first notified in 2006, and about 1,000 acres were later acquired and allotted through the Karnataka Industrial Areas Development Board during the following state government's term. It was originally notified by former Chief Minister HD Kumaraswamy in 2006 and that approximately 1,000 acres were acquired and allotted by the Karnataka Industrial Areas Development Board during the subsequent Bharatiya Janata Party (BJP) government.

The current cycle began with a cabinet decision in January 2025. The township proposal received Cabinet approval in January 2025, following which the GBDA issued a preliminary land acquisition notification in March 2025, proposing to acquire 7,481 acres across nine villages. In May 2026, the Cabinet approved a revised proposal covering the same extent.

Land is being acquired under the Karnataka Urban Development Authorities Act, 1987. Three villages, Kempainapalya, Vaderahalli, and Mandalahalli are notified in the Gazette under Section 19(1) of the KUDA Act for the implementation of a development scheme, deemed as public purpose.

Planning horizon

The master plan is being framed for the long term. As part of the master-planning exercise, studies will be conducted on population growth, demographic trends and economic expansion to estimate infrastructure requirements for the next three decades. A separate statement from the GBDA commissioner's side describes the planning work as covering a much wider area: "Our goal is to complete land acquisition within a year while simultaneously preparing a master plan for the entire 30,000-acre area to ensure planned growth and connectivity."

Total planned area and what is developed

Reported figures for the township itself differ, mainly because the boundary has changed over time. The figures below are dated and should be read as separate measures.

Built-out area by a target year has not been set out in the reporting I could read. The only dated target in mid-2026 reporting is that the township targeted for phased completion over the next three years.

Land-use split

The best-documented split comes from the original plan, when the township was 9,684 acres. As per the original plan, the Bidadi township project is spread over 9,684 acres, including 2,725 acres of government and 6,959 acres of private land. Besides residential plots (25 per cent of the total land), the township will have land for economic activities (25 per cent), roads and utilities (25 per cent), park and open spaces (15 per cent) and civic amenity space (10 per cent).

A later breakdown of the 9,600-acre footprint gives a different picture. Of the total proposed area, around 1,800 acres have been earmarked for residential layouts, while 5,681 acres are to be developed as bulk land for multi-storied buildings. Nearly 44.5% of the total land area is projected to constitute saleable space.

Phases and land tranches

The township is to be built in phases. The 8,943-acre township will be developed in phases. An earlier proposal for the pooled-land approach said the plan is to build the integrated township in three phases. The table covers the land acquisition tranches that have been notified.

Population and employment

No population or job target is set in the sources I reviewed. The consultant's brief covers the studies that will produce those numbers. As part of the planning exercise, the consultant will study population growth trends, demographic changes and economic development patterns to estimate infrastructure requirements over the next three decades. The land plan also includes dedicated sectors for different industries along with residential facilities.

Planner and consultant

GBDA is the agency running the planning. The consultancy work, to be executed over 12 months, will be carried out in four phases — preparation of the master plan, land allocation, DPR preparation and project management support. The scope also covers concept plans, master plans, land-use strategies, infrastructure frameworks, developer selection models, implementation roadmaps and investor mobilisation plans. A Rs 26-crore tender to appoint a planning consultant opened only last week. The consultant's name has not been reported in the sources I used. Earlier, the BMRDA will be the special purpose vehicle and Local Planning Authority for both the projects.

Location and access

Access is planned around several road links. Located about 25 km from Bengaluru, the township will be well-connected by five major roads. Reported distances vary: about 40 kilometres from Bengaluru in another account. A proposed 40-km network linking major roads and rail systems is part of the connectivity plan. Two of the three shortlisted sites for Bengaluru's second international airport are in close proximity to the township.

Official documents

Acquisition notices are published under the Karnataka Urban Development Authorities Act, 1987, and appear in the state Gazette, as described above. The governance law that places GBDA-linked planning within Bengaluru's wider structure is the Greater Bengaluru Governance Act, 2024, which lists the Greater Bengaluru Authority as one of the civic authorities in the Greater Bengaluru Area. The consultant tender and draft plans are issued by GBDA, so the GBDA notices and the Gazette are the places to check for the master plan once it is published.

Development phases

Acquisition notice 1June 2026About 499 acres in Kempayyanapalya, Mandalahalli andVaderahalli villagesAcquisition notice 215 July 2026Over 4,941 acres in four villagesAcquisition notice 330 October 20261,895 acres in Kanchugaranahalli and Byramangalavillages

Land use

Residential25%Economic activities25%Roads and utilities25%Parks and open spaces15%Civic amenity10%

Frequently asked questions

How big is the Bidadi township master plan area?

The township is proposed on 7,481 acres across nine villages, with another 2,742 acres for economic corridors, as of mid-2026. Other reports give a wider footprint of about 9,600 acres.

Has the Bidadi township master plan been finalised?

No

What is the planning horizon for the Bidadi township?

The master planning study looks 30 years ahead, covering population growth, demographic trends and economic expansion to estimate infrastructure needs.

What is the land-use split in the Bidadi township plan?

In the original plan, 25% of land was for residential plots, 25% for economic activities, 25% for roads and utilities, 15% for parks and open space and 10% for civic amenities.

How much land has been notified for acquisition so far?

As of November 2026, final acquisition notices cover over 7,335 acres across several villages. Acquisition is the legal step to obtain land and does not mean the land is built up.

Sources