Land Acquisition Record
Greater Bengaluru Integrated Township: Preliminary Land Acquisition Notice, March 2025
On 12 March 2025 the Greater Bengaluru Development Authority (GBDA) issued a preliminary land acquisition notification for the Greater Bengaluru Integrated Township (GBIT) at Bidadi, about 25 km from Bengaluru, affecting roughly 10,450 landowners. As of 12 November 2026 the township is Upcoming, and final land acquisition notices now cover over 7,335 acres across nine villages.

| Decision | Preliminary land acquisition notification for the Bidadi township |
|---|---|
| Decision body | Greater Bengaluru Development Authority (GBDA) |
| Decision date | 12 March 2025 |
| Landowners affected | About 10,450, as reported |
| Villages named in the preliminary notice | Nine: Allalasandra, Kanchugaranahalli Kaval, Gollarapalya, Kempaiahnapalya, Bannigere, Byaramangala, Mandlahalli, Hosur and Vaderahalli |
| Area reported for acquisition | 8,943 acres in one report; 7,481 acres across nine villages in another |
| Landowner return | 40% of developed land in return for surrendering land rights, per the GBDA Commissioner |
| Location | Bidadi hobli, Ramanagara taluk, about 25 km from Bengaluru |
| Status as of 12 November 2026 | Upcoming. Land is notified in all nine villages; the township is at the land and planning stage |
What GBDA decided on 12 March 2025
On 12 March 2025 GBDA issued a preliminary notification to acquire land for the Bidadi township, also searched as GBIT, Bidadi Township or Bidadi Integrated Township. The notice covered roughly 10,450 landowners. It was the first formal step in acquiring the land for a planned work-live-play township on the Bidadi side of Bengaluru.
The township was to be developed in phases. Officials said the government had already approved the township's development scheme before the notice was issued. Land acquisition was to follow the model the Bangalore Development Authority (BDA) has used for residential layouts, according to GBDA officials.
A preliminary notice opens the acquisition process. It does not by itself complete the transfer of land. Final notices, compensation and possession come later, as the record below shows.
Villages, acres and landowners in the notice
The preliminary notice named nine villages: Allalasandra, Kanchugaranahalli Kaval, Gollarapalya, Kempaiahnapalya, Bannigere, Byaramangala, Mandlahalli, Hosur and Vaderahalli.
Reports give different totals for the area. One report cites 8,943 acres for acquisition. Another cites 7,481 acres across nine villages for the preliminary notification. Both figures are attributed to the sources named in this record.
Separately, GBDA planned to acquire 2,742 acres to build five Economic Corridors. These were to link the township to Kanakapura Road, Mysuru Road, NICE Road and the planned Satellite Town Ring Road (STRR).
Terms offered to landowners
GBDA Commissioner P Rajendra Cholan said landowners would receive 40% of developed land in return for surrendering their land rights. The acquisition approach follows the BDA's residential layout model.
A later BMRDA approval report describes a further model, proposed in the state's review of options. Under it, landowners would receive developed land, including 1,000 sq yd residential plots and 200 to 300 sq yd commercial plots per acre within 5 km of the township, plus an annuity. Landless families would receive 10 years of pension. This is described as a proposal in the reports and is not a settled term of the 2025 notice.
Background to the March 2025 notice
- January 2025: Cabinet approval of the original proposal, per TheNewsMinute.
- 9 March 2025: The state government expanded GBDA's jurisdiction by 92 sq km through the addition of 22 villages. GBDA's total area became 233 sq km across 59 villages, and it was to oversee about 23,000 acres across those 22 villages besides the township land.
- 12 March 2025: Preliminary land acquisition notification for the township.
Officials said the jurisdiction expansion was needed to plan connectivity ahead of township work. The project had been delayed for almost two decades before it was revived.
What has happened since the notice
- 7 May 2026: Government approval for the project. The Cabinet approved a revised proposal covering the same 7,481 acres as the earlier proposal.
- June 2026: First final notifications for villages including Kempayyanapalya, Mandalahalli and Vaderahalli. Reports give about 499 acres, and other outlets report about 518 acres.
- 15 July 2026: Second final notification covering over 4,941 acres in four villages.
- 2 November 2026: Final notifications under Section 19(1) of the Karnataka Urban Development Authorities Act, 1987, for about 1,895 acres in Byramangala and Kanchugaranahalli, Bidadi Hobli, Ramanagara taluk. The total under final notices is over 7,335 acres across nine villages.
- 11 November 2026: Reports say the BMRDA, which chairs the planning for both projects, formally approved the township and the STRR. A HUDCO loan offer of up to Rs 21,000 crore was also reported.
The final notifications enable compensation payments and steps towards securing possession of the land. Compensation is to be determined under the applicable land acquisition framework.
What this means for landowners and buyers
As of 12 November 2026 the township is Upcoming. The land has been notified, but the township itself is still at the land and planning stage. A consultant tender worth Rs 26 crore, for a 12-month master plan and detailed project report, was floated in June 2026. Its scope covers roads, parks, civic amenities, and land for industrial and commercial use.
The government estimate is Rs 18,133 crore. An earlier report gave Rs 20,000 crore, and another gave Rs 22,000 crore. The civil works component is estimated at Rs 6,580 crore.
Opposition is active. A social media campaign under the hashtag #SaveBidadi, starting 1 November 2026, cites ecological risks. An NGO has asked the National Green Tribunal to take suo motu cognisance. A section of landowners continues to oppose the acquisition.
Developer and planning authority
GBDA is the implementing authority for the township. Its Commissioner, P Rajendra Cholan, also heads the Bengaluru Metropolitan Region Development Authority (BMRDA). BMRDA is the special purpose vehicle and Local Planning Authority for both the township and the STRR. Both projects are to be developed under a Development Plan and Town Planning Scheme under the Town and Country Planning Act, 1961.
Locality context: Bidadi and Ramanagara
Bidadi lies in Ramanagara district, about 25 km from Bengaluru. The township is to be connected by five major roads. Two of the three shortlisted sites for Bengaluru's second international airport are close to the township, according to reports. The township area is reported as 9,178.29 acres in 10 villages, made up of 643 acres of water bodies, 6,336.33 acres of private land and 2,198.21 acres of government land. The Regional Township Authority would cover 38 more villages in the Bidadi, Kailancha and Ramanagaram hoblis.
Frequently asked questions
What did GBDA decide about the Bidadi township?
On 12 March 2025 GBDA issued a preliminary land acquisition notification for the Greater Bengaluru Integrated Township at Bidadi, affecting roughly 10,450 landowners across nine named villages.
What does the township's land acquisition offer landowners?
GBDA Commissioner P Rajendra Cholan said landowners would receive 40% of developed land in return for surrendering their land rights.
What is the status of the Bidadi township as of November 2026?
As of 12 November 2026 the township is Upcoming. Final notices cover over 7,335 acres across nine villages, and the township is still at the land and planning stage.
Where is the Greater Bengaluru Integrated Township located?
The township is in Bidadi hobli, Ramanagara taluk, about 25 km from Bengaluru, and is being developed by the Greater Bengaluru Development Authority.
What is the estimated cost of the Bidadi township project?
The government estimate is Rs 18,133 crore. An earlier report gave Rs 20,000 crore, and another report gave Rs 22,000 crore.
Sources
- Govt begins land acquisition process to develop Bidadi township (Deccan Herald, March 2025)
- Greater Bengaluru Development Authority expands jurisdiction, takes over 22 more villages (Deccan Herald, 9 March 2025)
- Karnataka cabinet approves decision to develop satellite townships around Bengaluru (Deccan Herald)
- Karnataka issues final land acquisition notification for Greater Bengaluru township (The News Minute)
- Karnataka government issues final notification to acquire land for Bidadi project (Deccan Herald, 2 Nov 2026)
- Final notification issued for Greater Bengaluru Integrated Township land acquisition near Bidadi (NammaAward)
- Karnataka issues final gazette for Bidadi Township, farmers intensify land protest (NewsFirst)
- Bidadi Integrated Township gets boost with Rs 21,000-cr HUDCO loan offer (Deccan Herald)
- Bidadi township, Satellite Town Ring Road approved by BMRDA (Deccan Herald)
- Bidadi township moves ahead despite opposition; 26-crore tender floated for master plan of 18,133-crore project (NewsFirst)
- SaveBidadi campaign on November 1 to oppose township (Deccan Herald)
- Bidadi GBIT project, land acquisition process and compensation raises critical questions (Citizen Matters)