City planning
Bidadi township takes its planning step: Rs 26-crore master plan tender for Bengaluru's outskirts
The Greater Bengaluru Development Authority (GBDA) floated a Rs 26-crore tender in June 2026 to hire a consultant for the master plan and detailed project report (DPR) of the Greater Bengaluru Integrated Township at Bidadi, about 25 km from Bengaluru. The 12-month work covers roads, parks, civic amenities and land for industrial and commercial use.

| Consultant tender | Rs 26 crore, floated June 2026; bids scheduled to open June 24, 2026 |
|---|---|
| Contract length | 12 months |
| Implementing authority | Greater Bengaluru Development Authority (GBDA) |
| Location | Bidadi hobli, Ramanagara taluk, about 25 km from Bengaluru |
| Notified land (as of 2 November 2026) | Over 7,335 acres across nine villages under final notifications |
| Project cost estimates | Rs 18,133 crore (government estimate); Rs 20,000 crore in an earlier report; about Rs 22,000 crore in a later report |
| Status (as of 11 November 2026) | Upcoming. Land is notified in all nine villages, but the township is not built. BHK types and prices not yet announced |
What GBDA has tendered
GBDA has invited bids for a consultant to prepare the master plan and DPR for the township, which is also referred to in reports as Bidadi AI City. The tender was floated in June 2026, with bids scheduled to open on June 24, 2026. The engagement is for 12 months and includes project management.
The planning consultant is therefore being brought in before the township's detailed layout is settled, which makes the next year a key test of how the project is designed.
What the consultant will produce
The scope set out in the tender goes beyond a single plan document. The consultant is expected to deliver:
- a concept plan and a full master plan
- a land-use strategy
- an infrastructure framework covering the road network, parks and civic amenities
- land parcels for industrial and commercial use
- a developer selection model and an investor mobilisation plan
The consultant will also help GBDA attract investors and development partners, so the tender links planning directly to how the township will be funded and built.
The numbers behind the project
Cost figures differ between reports, so the table below shows each one with its source type.
| Item | Amount |
|---|---|
| Master plan and DPR consultant tender | Rs 26 crore |
| Civil works component (estimate) | Rs 6,580 crore |
| Total project cost (government estimate) | Rs 18,133 crore |
| Total project cost (earlier report) | Rs 20,000 crore |
| Estimated land acquisition cost | Rs 10,000 crore |
| HUDCO loan offer (up to) | Rs 21,000 crore |
GBDA Commissioner P Rajendra Cholan has said the authority will draw on the HUDCO loan only as needed. The loan is expected to speed up land acquisition and civil works, a project that was delayed for almost two decades before it was revived.
Land acquisition and the protests
GBDA has moved to final notifications under Section 19(1) of the Karnataka Urban Development Authorities Act, 1987, in three stages:
- June 2026: first final notification covering Kempayyanapalya, Vaderahalli and Mandalahalli, about 499 acres in one report and about 518 acres in others
- July 15, 2026: second final notification covering over 4,941 acres in four villages
- November 2, 2026: final notification for about 1,895 acres in Byramangala and Kanchugaranahalli
Compensation disbursal was being initiated while the tender was floated. Deputy CM D K Shivakumar has said that 80% of farmers support the project and that no land will be denotified.
Opposition is continuing. Forty farmer organisations were preparing to move court, alleging that GBDA has not obtained the consent of 80% of affected landowners. A #SaveBidadi campaign on X began on November 1, 2026, citing ecological risks. The NGO Bidadi Geleyara Balaga has asked the National Green Tribunal to take suo motu cognisance, citing lakes, coconut and other trees and livestock in the area.
What it means for Bengaluru's outskirts
For land, the plan sets out industrial and commercial parcels alongside residential areas, so the township is meant to bring jobs closer to homes rather than only add housing. For roads, the township is to be connected by five major roads, and reports say two of three shortlisted sites for Bengaluru's second international airport lie close to it.
GBDA's jurisdiction was extended in March 2025 by 92 square km with 22 more villages, taking it to 233 square km across 59 villages, so the authority now plans the growth around the township. Buyers and residents should note that the township is at the land and planning stage. It is not yet built, and no plots, flats or prices have been announced.
What comes next
The consultant's 12-month work will produce the master plan and DPR, which will then support the developer selection model and investor outreach. Further final land notifications and compensation payments will follow the notified villages, and the protests and court challenges will run alongside. Until a master plan is finalised and a developer is chosen, the township remains an upcoming project.
Facts as on 11 November 2026, from RERA / the developer.
Frequently asked questions
How much is the GBDA tender for the Bidadi township master plan?
GBDA floated a Rs 26-crore tender in June 2026 to hire a consultant for the master plan and detailed project report of the township.
How long will the master plan consultant work on the Bidadi township?
The consultant's engagement is for 12 months and covers the concept plan, master plan, land-use strategy, infrastructure framework and investor mobilisation plan.
Are plots or flats on sale in the Greater Bengaluru Integrated Township?
No BHK types or prices have been announced, and the township is still at the land and planning stage with a status of Upcoming as of November 2026.
How much land has been notified for the Bidadi township?
Final notifications cover over 7,335 acres across nine villages as of November 2, 2026, following notices in June and July 2026 and the latest one covering about 1,895 acres.
Where is the Greater Bengaluru Integrated Township located?
The township is in Bidadi hobli of Ramanagara taluk, about 25 km from Bengaluru, and is being developed by GBDA.
Why are farmers opposing the Bidadi township?
Forty farmer organisations are preparing to move court, alleging GBDA has not obtained consent from 80% of affected landowners, and campaigners cite ecological risks to lakes, trees and livestock.
Sources
- Bidadi township: what the project is, who opposes it and why
- Bidadi township moves ahead despite opposition; 26-crore tender floated for master plan of 18,133-crore project
- Bidadi AI City moves ahead despite protests; GBDA floats 26-crore tender
- Karnataka's AI City is 2006's failed Bidadi township under a new name
- Karnataka government issues final notification to acquire land for Bidadi project
- Bidadi Integrated Township gets boost with Rs 21,000-cr HUDCO loan offer
- Greater Bengaluru Development Authority expands jurisdiction, takes over 22 more villages
- Final notification issued for Greater Bengaluru Integrated Township land acquisition near Bidadi
- Savebidadi campaign on November 1 to oppose township