New Cities India

Industrial Development

Hisar IMC Moves Forward with ₹707-Crore Trunk Infrastructure Tender

In a crucial step towards setting up of the Integrated Manufacturing Cluster (IMC), the Haryana project of the National Industrial Corridor Development Corporation (NICDC) has taken first step as the tender worth Rs 707 crore has been floated for developing infrastructure in about 2,988 acres near the Maharaja Agrasen airport in Hisar town. It is the first IMC project to take shape, as the required land was made available without any hurdles since it is being developed on government-owned land.

Hisar Industrial Smart City — Hisar IMC Moves Forward with ₹707-Crore Trunk Infrastructure Tender
Tender Amount₹707 crore, excluding operation and maintenance (O&M) costs and GST
Tender TypeEngineering, Procurement and Construction (EPC) basis, covering design, construction, testing, commissioning and operation and maintenance of the cluster's trunk infrastructure
Project Area2,988 acres with independent and direct access from NH 9 and NH 52
Total Project Cost₹4,680 crore with investment potential of ₹32,417 crore
Employment GenerationExpected to generate 1.25 lakh jobs
Construction TimelineSuccessful bidder must complete construction work within 30 months and maintain infrastructure for five years
Implementing AgencyNICDC Haryana Integrated Manufacturing Cluster Hisar Project Limited (NHIMCHPL)
Number of IMC ProjectsAmong 12 IMCs conceptualised by NICDC to create world-class industrial infrastructure
Multi-Modal Connectivity PhasesPhase 1 (2027) via Hisar city Junction, freight terminal at airport by 2032, final phase by 2037
Tender StatusIssued via e-tendering process in late June 2026

The Tender Announcement

The tender worth Rs 707 crore has been floated for developing infrastructure in about 2,988 acres near the Maharaja Agrasen airport in Hisar town. The NICDC Haryana Integrated Manufacturing Cluster Hisar Project Limited (NHIMCHPL) has floated this tender for the development of trunk infrastructure at the proposed IMC in Hisar under the Amritsar-Kolkata Industrial Corridor (AKIC).

The project will be executed on an Engineering, Procurement and Construction (EPC) basis and cover the design, construction, testing, commissioning and operation and maintenance of the cluster's trunk infrastructure.

Breaking Years of Planning Deadlock

Years after approval, the project remained largely confined to the planning stage. The tender announcement in late June 2026 represents the first concrete action toward physical implementation. The project is the first IMC to take shape, as the required land was made available without any hurdles since it is being developed on government-owned land. Nearly 2,988 acres of encumbrance-free government land has already been transferred by the state government.

Scope and Infrastructure Components

The trunk infrastructure package includes essential utilities required for the cluster's operation. It includes roads, water supply, sewerage, stormwater drainage, etc to be constructed within 30 months of tender award. Additionally, DHBVN will build a 220-kV electric substation with five 33-kV substations for the project.

Broader Project Context

An Industrial Manufacturing Cluster (IMC) has been proposed to be developed in Hisar, Haryana, adjacent to the Hisar Airport under Amritsar Kolkata Industrial Corridor (AKIC). The project is among the 12 IMCs conceptualised by the National Industrial Corridor Development Corporation (NICDC) to create world-class industrial infrastructure and attract large-scale manufacturing investments.

With an investment potential of ₹32,417 crore and a project cost of ₹4,680 crore, it is expected to generate 1.25 lakh jobs.

Strategic Location and Connectivity

The site is located adjacent to the proposed International Airport Hub (IAH) at Hisar along the intersection of NH 9 and NH 52. Hisar is strategically located between Rewari (Western Dedicated Freight Corridor station) and Ambala (Eastern Dedicated Freight Corridor station) connected to both stations with feeder rail links.

The IMC will benefit from multi-modal connectivity with air, road and rail initially through the Hisar city Junction in the first phase of its development (2027) and the rail terminal for freight in the airport by 2032 and final phase (2037).

What Comes Next

The successful bidder will have to complete the construction work within 30 months and maintain the infrastructure for five years. The contract also provides for a 60-month defect liability period from the date of issuance of the completion certificate.

Once the trunk infrastructure is completed, the cluster will be ready to attract anchor tenants and manufacturing units across multiple sectors including aerospace, defence, food processing, and specialized engineering.

Development phases

Phase 1 – Trunk Infrastructure2026–2029 (30 months from tender award)Internal roads, water supply, sewerage, stormwaterdrainage, electrical substations, and core utilitiesacrossPhase 2 – Cluster Development2029–2032Plot allotment, facility operationalization, and earlyindustrial unit setup; rail freight terminal at HisarAirportPhase 3 – Full Operationalization2032–2037Complete multi-modal connectivity, full freightcorridor integration, aerocity development, andaerospace/defence

Frequently asked questions

Why is Hisar IMC the first IMC among 12 to actually move to implementation?

The required land was made available without any hurdles since it is being developed on government-owned land. Unlike other IMC projects that require private or disputed land acquisition, Hisar benefited from pre-available state land, eliminating acquisition delays.

What is the difference between the ₹707-crore tender and the ₹4,680-crore total project cost?

The ₹707-crore tender covers only trunk infrastructure (roads, utilities, basic facilities). The ₹4,680-crore total project cost includes all development phases—land preparation, sector-specific zones, industrial plots, commercial areas, and ancillary facilities—spread over Phase 1 and Phase 2 (by 2032).

How is the cluster connected to the airport?

The site is located adjacent to the proposed International Airport Hub (IAH) at Hisar along the intersection of NH 9 and NH 52. The cluster will serve as a logistics and manufacturing gateway for the airport's cargo and MRO (maintenance, repair, operations) functions.

Which sectors will the cluster support?

IMC Hisar will support industries in engineering, auto components, textiles, agro-processing, electronics, and logistics, while also integrating sustainability and green infrastructure practices.

When will the cluster be operational?

Construction must be completed within 30 months from tender award. If awarded immediately, trunk infrastructure would be ready by 2029, with full cluster operationalization targeted by 2037.

Who is issuing the tender?

The tender has been issued through the e-tendering process by NHIMCHPL, a special purpose vehicle jointly promoted by the Centre and the Haryana Government.

Sources

Interested in Hisar Industrial Smart City?

Register once — get informed when projects, plot schemes or launches open up here.