Hisar IMC Breaking Past Planning: Rs 707-Crore Infrastructure Tender Launched

The Haryana project of the National Industrial Corridor Development Corporation (NICDC) has taken first step as the tender worth Rs 707 crore has been floated for developing infrastructure in about 2,988 acres near the Maharaja Agrasen airport in Hisar town. The Rs 707 crore EPC tender for design and construction was issued in June 2026.

Hisar Industrial Smart City — Hisar IMC Breaking Past Planning: Rs 707-Crore Infrastructure Tender Launched
Total land area2,988 acres
EPC tender valueRs 707 crore
Project cost (full development)₹4,680 crore
Investment potential₹32,417 crore
Expected job creation1.25 lakh jobs
Infrastructure construction timelineWithin 30 months of tender award
Trunk infrastructure scopeRoads, water supply, sewerage, stormwater drainage; 220-kV electric substation with five 33-kV substations
First IMC to reach EPC phaseFirst IMC project to take shape, as the required land was made available without any hurdles since it is being developed on government-owned land
Development phasesFirst phase operational by 2027, rail terminal by 2032, final phase by 2037

From Planning Limbo to Tender Launch

The sluggish pace of work has been leading to delays in the proposed Integrated Manufacturing Cluster near the airport in Hisar, with government sources indicating that delays in on-ground execution, despite strong initial structural advantages, are a matter of concern. But on June 29, 2026, the National Industrial Corridor Development Corporation floated the Rs 707 crore tender for developing infrastructure in about 2,988 acres.

Despite having land acquisition completed—one of the biggest bottlenecks in industrial corridor development nationwide—procedural progress had remained slow, with the appointment of consultants still under process and the EPC tender yet to be floated as of early June 2026. The tender launch marks an inflection point: the ambitious Integrated Manufacturing Cluster project has taken its first step towards implementation.

What the Tender Covers

The NICDC Haryana Integrated Manufacturing Cluster Hisar Project Limited (NHIMCHPL) has floated the tender for the development of trunk infrastructure at the proposed IMC under the Amritsar-Kolkata Industrial Corridor. The infrastructure includes roads, water supply, sewerage, stormwater drainage, etc. to be constructed within 30 months of tender award. Additionally, the Dakshin Haryana Bijli Vitran Nigam (DHBVN) will build a 220-kV electric substation with five 33-kV substations for the project.

When completed, the IMC is expected to require around 232 MW of electricity.

Strategic Context: Who Decided and Why Urgency

The project is being developed under the National Industrial Corridor Development Corporation (NICDC) as part of the Amritsar–Kolkata Industrial Corridor (AKIC). In a high-level review meeting held on April 15, Chief Secretary Anurag Rastogi reviewed the progress of the IMC-Hisar project and directed all concerned departments to ensure timely and expedited implementation of decisions related to the project.

The project gains significance as Hisar is emerging as an aerospace and advanced manufacturing hub, especially in view of the developing ecosystem around Maharaja Agrasen Airport. Concerns are being raised in regional industrial circles about potential investment diversion, including the proposed trainer aircraft manufacturing initiative associated with Shakti Aircraft Industries. Experts said sectors such as aerospace, defence-linked manufacturing and advanced engineering are particularly sensitive to ecosystem readiness, logistics connectivity and implementation certainty, making execution timelines crucial.

The Rajpura Comparison

The slow pace is more evident when compared with other corridor-linked projects such as the IMC at Rajpura, where EPC-level execution has already advanced, strengthening investor confidence. Industry experts maintain that in the current competitive investment environment, execution speed is as critical as policy intent, particularly as states compete aggressively for manufacturing investments amid global supply chain diversification under the "China Plus One" strategy.

What Comes Next

The IMC will benefit from multi-modal connectivity with air, road and rail initially through the Hisar city Junction in the first phase of its development (2027) and the rail terminal for freight in the airport by 2032 and final phase (2037).

The 30-month construction window for trunk infrastructure—if bid evaluation and award follow normal timelines—positions physical work to commence in late 2026 or early 2027. The IMC is projected as a transformative industrial smart city expected to reshape the economic landscape of western Haryana.

Development phases

Phase 1by 20271,605 acres; first-phase industrial development;multimodal connectivity via highway and airPhase 2by 2032Rail freight terminal at Maharaja Agrasen Airport;additional industrial and logistics infrastructurePhase 3 (Final)by 2037Complete 2,988-acre cluster; full multimodal hub;aerospace and defence manufacturing hub

Frequently asked questions

Why did the IMC-Hisar project face procedural delays despite having land ready?

Consultant appointment and engineering-level planning remained slow, with the appointment of consultants still under process and the EPC tender yet to be floated as of early June 2026.

What does the Rs 707 crore tender include?

Roads, water supply, sewerage, stormwater drainage, and electrical infrastructure including a 220-kV grid substation and five 33-kV substations.

How long will the infrastructure construction take?

Within 30 months of tender award.

What is Shakti Aircraft Industries and why is it relevant?

Sakthi Aircraft Industry is investing ₹500 crore in trainer aircraft manufacturing in Hisar, with planned expansion to ₹1,500 to 2,000 crore over 2–3 years. Concerns are being raised about potential investment diversion given Hisar's emerging role as an aerospace and advanced manufacturing hub.

How does Hisar IMC compare to other IMC projects?

It is the first IMC project to take shape, as the required land was made available without any hurdles since it is being developed on government-owned land. However, EPC-level execution at the IMC at Rajpura has already advanced.

When will industries begin operations?

First phase of development targets 2027, with the rail terminal for freight at the airport by 2032 and final phase by 2037.