Land Acquisition Notice
Greater Bengaluru Integrated Township: First Final Land Notification, June 2026
The Greater Bengaluru Integrated Township, also searched as Bidadi Township, is a planned work-live-play township about 25 km from Bengaluru, being developed by the Greater Bengaluru Development Authority (GBDA). In June 2026 the state issued the first final land acquisition notification for Kempayyanapalya, Vaderahalli and Mandalahalli villages, and as of 11 November 2026 the township is Upcoming, with no BHK types or prices announced.

| Status (as of 11 November 2026) | Upcoming. Land has been notified in all nine villages, but the township has not been built. |
|---|---|
| Developer | Greater Bengaluru Development Authority (GBDA) |
| Notification reported | 13 June 2026, first final notification |
| Villages in this notification | Kempayyanapalya, Vaderahalli and Mandalahalli |
| Area in this notification | 499 acres in one report; about 518 acres in other reports |
| Legal basis | Section 19(1) of the Karnataka Urban Development Authorities Act, 1987 |
| Preliminary notification | March 2025 |
| Location | Bidadi hobli, Ramanagara taluk, Ramanagara district; some reports place it in Bengaluru South district |
| Reported project cost | Estimates range from Rs 18,133 crore to Rs 22,000 crore across reports |
What was decided in June 2026
Facts as on 11 November 2026, from RERA / the developer.
The Karnataka government issued the first final notifications for land acquisition for the Greater Bengaluru Integrated Township near Bidadi in June 2026. One report of the notification is dated 13 June 2026. The notification covered Kempayyanapalya, Vaderahalli and Mandalahalli villages in the Ramanagara-Harohalli region, which is part of the Bidadi growth corridor.
The notification was issued under Section 19(1) of the Karnataka Urban Development Authorities Act, 1987. It followed the preliminary notification that GBDA issued in March 2025. Government approval for the project was granted on 7 May 2026, and the Cabinet approved a revised proposal in May 2026 covering the same extent as the earlier proposal of 7,481 acres.
| Item | Detail |
|---|---|
| Type of decision | First final land acquisition notification |
| Issuing body | Karnataka government, for the Greater Bengaluru Development Authority |
| Reported date | June 2026 (one report dated 13 June 2026) |
| Villages | Kempayyanapalya, Vaderahalli, Mandalahalli |
| Area | 499 acres (one report); about 518 acres (other reports) |
| Legal basis | Section 19(1), Karnataka Urban Development Authorities Act, 1987 |
| Earlier step | Preliminary notification, March 2025 |
| Government approval | 7 May 2026 |
What the notice means in practice
The notification starts the formal acquisition of the listed land. Compensation is to be determined under the applicable land acquisition framework. Later reports on the same project say that final notifications enable compensation payments and steps towards taking possession of the land.
GBDA has said that landowners would receive 40% of developed land in return for surrendering their land rights. This was stated when the preliminary notification was issued in March 2025, and the terms of the final compensation are still to be settled under the framework.
Deputy Chief Minister D K Shivakumar said in May 2026 that he would not denotify any land. The government has also repeated its claim that 80% of farmers support the project. Owners of land in the listed villages should read the gazette entry for their survey numbers, since the notice applies to specific land parcels.
- The township itself has not been built, and its status is Upcoming as of 11 November 2026.
- No BHK types, carpet areas or prices have been announced.
- No possession date has been announced.
Steps before and after this notice
The notification is one step in a sequence that began with a Cabinet decision and has continued through several final notices. The main steps are set out below.
- January 2025: Cabinet approval of the original proposal, as reported.
- 9 March 2025: The state expanded GBDA's jurisdiction by 92 square km with 22 more villages, to plan connectivity before township work starts.
- 12 March 2025: GBDA issued the preliminary land acquisition notification, which affected about 10,450 landowners.
- 7 May 2026: Government approval for the project was granted.
- June 2026: First final notification, covering Kempayyanapalya, Vaderahalli and Mandalahalli.
- 15 July 2026: Second final notification, covering over 4,941 acres in four villages.
- 2 November 2026: Final notification for about 1,895 acres in Byramangala and Kanchugaranahalli. Reports say total land under final notifications now exceeds 7,335 acres.
- November 2026: The BMRDA meeting approved the township and the Satellite Town Ring Road, and a Rs 26-crore tender was floated for the master plan and Detailed Project Report, with a 12-month engagement.
The HUDCO loan offer of up to Rs 21,000 crore is reported to fast-track land acquisition and civil works. GBDA has said it would draw on the loan only as needed. The estimated land acquisition cost is Rs 10,000 crore, and the civil works component is estimated at Rs 6,580 crore.
Opposition and open questions
Farmers, activists and citizens have opposed the township, citing ecological risks. A social media campaign under the hashtag #SaveBidadi was set to begin on 1 November 2026.
The NGO Bidadi Geleyara Balaga has asked the National Green Tribunal to take suo motu cognisance of the project, and the NGO says the Tribunal has acknowledged the request. The NGO has said it will provide details of lakes and forest land that would be affected. The Karnataka High Court has dismissed a public interest petition against the Bidadi township.
Several questions remain open for buyers and landowners. Project cost estimates differ between Rs 18,133 crore and Rs 22,000 crore. The township area is given as about 7,300 acres in most reports, while the BMRDA approval describes a township area of 9,178.29 acres across 10 villages.
Frequently asked questions
What did the June 2026 Bidadi township notification cover?
The first final notification for the Greater Bengaluru Integrated Township covered Kempayyanapalya, Vaderahalli and Mandalahalli villages, with an area reported as 499 acres in one report and about 518 acres in others.
Under which law was the Bidadi township land notification issued?
The notification was issued under Section 19(1) of the Karnataka Urban Development Authorities Act, 1987.
Who is developing the Greater Bengaluru Integrated Township?
The Greater Bengaluru Development Authority (GBDA) is developing the township, also searched as Bidadi Township.
What is the status of the Bidadi township as of November 2026?
As of 11 November 2026 the township is Upcoming, and the township has not been built.
Have BHK types or prices been announced for the Bidadi township?
No BHK types or prices have been announced for the Greater Bengaluru Integrated Township as of 11 November 2026.
How will landowners be compensated after the notification?
Compensation is to be determined under the applicable land acquisition framework, and GBDA has said landowners would receive 40% of developed land in return for surrendering their land rights.
Sources
- NammaAward: Final notification issued for Greater Bengaluru Integrated Township land acquisition near Bidadi
- The News Minute: Karnataka issues final land acquisition notification for Greater Bengaluru township
- Deccan Herald: Karnataka government issues final notification to acquire land for Bidadi project (2 Nov 2026)
- Deccan Herald: Govt begins land acquisition process to develop Bidadi township (March 2025)
- Deccan Herald: Karnataka cabinet approves decision to develop satellite townships around Bengaluru
- Deccan Herald: Greater Bengaluru Development Authority expands jurisdiction, takes over 22 more villages
- Deccan Herald: Final notification for Bidadi township by June-end, Shivakumar defends project
- Deccan Herald: Bidadi Integrated Township gets boost with Rs 21,000-cr HUDCO loan offer
- Deccan Herald: Bidadi township, Satellite Town Ring Road approved by BMRDA
- The News Minute: Bidadi township, what the project is, who opposes it and why
- NewsFirst: Karnataka issues final gazette for Bidadi Township, farmers intensify land protest
- Citizen Matters: Bidadi GBIT project, land acquisition process and compensation raises critical questions
- The South First: Karnataka HC dismisses PIL against Bidadi township
- Deccan Herald: SaveBidadi campaign on November 1 to oppose township