New Cities India

Government Decision

GBIT Bidadi Township: Karnataka Approval on May 7, 2026

The Greater Bengaluru Integrated Township (GBIT), also searched as Bidadi Township, is a planned work-live-play township about 25 km from Bengaluru, implemented by the Greater Bengaluru Development Authority (GBDA). Reports state that the Karnataka government granted approval for the current version of the project on May 7, 2026, and the status as of November 11, 2026 is Upcoming, with BHK types and prices not yet announced.

Greater Bengaluru Integrated Township (Bidadi) — GBIT Bidadi Township: Karnataka Approval on May 7, 2026
DecisionGovernment approval for the current version of the Greater Bengaluru Integrated Township (GBIT)
Date of approvalMay 7, 2026, as reported
Cabinet decisionRevised proposal approved in May 2026, covering the same extent of 7,481 acres
Extent7,481 acres across nine revenue villages
Implementing authorityGreater Bengaluru Development Authority (GBDA)
Legal basis for final notificationsSection 19(1), Karnataka Urban Development Authorities Act, 1987
LocationBidadi hobli, Ramanagara taluk, Ramanagara district; about 25 km from Bengaluru
Status as of November 11, 2026Upcoming. Land has been notified; the township has not been built

What was decided on May 7, 2026

Facts as on 11 November 2026, from government notifications and reports.

Reports state that the Karnataka government granted approval for the current version of the Greater Bengaluru Integrated Township on May 7, 2026. The township is planned as a work-live-play development on land around Bidadi, and the project is positioned as India's first AI-powered Work-Live-Play township.

In May 2026 the Cabinet also approved a revised proposal covering the same 7,481-acre extent. The Cabinet had approved the original proposal in January 2025. Reports cite both the May 7 approval and the Cabinet decision as key milestones, so this record lists both.

Decision timeline

The three final notifications cover three, four and two villages, which together account for the nine villages in the original preliminary notice.

Operative details of the approval

ItemDetail
Extent (revised proposal)7,481 acres across nine revenue villages
Villages named in the preliminary noticeAllalasandra, Kanchugaranahalli Kaval, Gollarapalya, Kempaiahnapalya, Bannigere, Byaramangala, Mandlahalli, Hosur and Vaderahalli
LocationBidadi hobli, Ramanagara taluk, Ramanagara district, with villages in Harohalli hobli. Some reports place it in Bengaluru South district
Regulating jurisdictionIn March 2025 the state expanded GBDA jurisdiction by 92 sq km with 22 more villages, taking the total to 233 sq km across 59 villages
Acquisition modelLandowners would receive 40% of developed land in return for surrendering land rights, according to GBDA Commissioner P Rajendra Cholan
Reported costGovernment estimate of Rs 18,133 crore. Other reports give Rs 20,000 crore and Rs 22,000 crore
Financing offeredHUDCO loan of up to Rs 21,000 crore
Civil works estimateRs 6,580 crore

Practical effect for landowners

The approval moved the project into the land acquisition stage. The final notifications issued under Section 19(1) of the Karnataka Urban Development Authorities Act, 1987 enable compensation payments and steps toward securing possession. Compensation is to be determined under the applicable land acquisition framework.

Deputy Chief Minister D K Shivakumar said in May 2026 that final notifications would be issued by the end of June for 7,481 acres. He also said that no land would be denotified. The government has repeatedly said that 80% of farmers support the project, a figure that opponents dispute.

What it means for buyers

The approval is a planning and acquisition step, not a launch. As of November 2026 the township has not been built, and no BHK types or prices have been announced. Buyers should treat any listing claims as unconfirmed until the implementing authority publishes its own plans, prices and timelines.

GBDA has floated a Rs 26-crore tender to appoint a consultant for the master plan and Detailed Project Report. The 12-month scope covers the concept plan, land-use strategy, infrastructure framework, developer selection model and investor mobilisation plan.

Opposition and open questions

A section of landowners continues to oppose land acquisition. A social media campaign under the hashtag #SaveBidadi was set to start on November 1, 2026, with farmers, activists and citizens citing ecological risks. The NGO Bidadi Geleyara Balaga has said it asked the National Green Tribunal to take suo motu cognisance, and that the tribunal acknowledged the request. The NGO has said the area supports over 10 lakh trees and a large livestock population.

These objections do not change the approval date, but they bear on how far and how quickly acquisition can proceed.

Frequently asked questions

When did the government approve the Bidadi GBIT township?

Reports state that the Karnataka government granted approval for the current version of the Greater Bengaluru Integrated Township on May 7, 2026.

Is the Bidadi township under construction?

As of November 2026 the township is Upcoming: land has been notified in all nine villages, but the township itself has not been built.

Which authority is implementing the Bidadi township?

The Greater Bengaluru Development Authority (GBDA) is implementing the project, and reports from November 2026 also name BMRDA as special purpose vehicle.

How much land is being acquired for the GBIT township?

Reports give 7,481 acres across nine revenue villages for the revised proposal approved in May 2026.

Have final land acquisition notifications been issued?

Yes. Final notifications were issued in June 2026, July 2026 and November 2026, and together they cover all nine villages.