Karnataka issues final gazette notifications for 1,895 acres for Greater Bengaluru Integrated Township

Greater Bengaluru Integrated Township (GBIT), also searched as Bidadi township, is a planned work-live-play township about 25 km from Bengaluru, being developed by the Greater Bengaluru Development Authority (GBDA). As of November 2026 its status is Upcoming: on 2 November 2026 the Karnataka government issued final land acquisition notifications for about 1,895 acres in Byramangala and Kanchugaranahalli, no BHK types or prices have been announced, and reported project cost estimates range from Rs 18,133 crore to about Rs 22,000 crore.

Greater Bengaluru Integrated Township (Bidadi) — Karnataka issues final gazette notifications for 1,895 acres for Greater Bengaluru Integrated Township
Decision date2 November 2026 (as reported)
Decision typeFinal land acquisition notifications
Area in this noticeAbout 1,895 acres
VillagesByramangala and Kanchugaranahalli, Bidadi Hobli, Ramanagara taluk, Ramanagara district
Total under final noticesOver 7,335 acres across nine villages (as of 2 November 2026)
Executing authorityGreater Bengaluru Development Authority (GBDA)
StatusUpcoming (as of November 2026)
Reported project costRs 18,133 crore (government estimate) to about Rs 22,000 crore (one report)
Distance from BengaluruAbout 25 km

What the 2 November 2026 notification decided

The Karnataka government issued final land acquisition notifications for about 1,895 acres in Byramangala and Kanchugaranahalli villages of Bidadi Hobli, Ramanagara taluk, for the Greater Bengaluru Integrated Township. The notice is the latest of the final acquisition steps for the township.

The notifications allow the government to proceed with compensation payments and take steps toward securing possession of the land. They do not yet mean that homes are being built or sold. The township itself remains at the land and planning stage.

The project has not been paused. The government has announced a four-member committee to collect feedback from landowners, but the notifications were issued before that committee has made its recommendations.

How the final notices add up across nine villages

The township area has now moved from preliminary notice to final notice in stages. Each stage covers a different set of villages.

Final noticeDateVillagesArea
FirstJune 2026Kempayyanapalya, Mandalahalli, VaderahalliAbout 499 acres (one report says about 518 acres)
Second15 July 2026Four villagesOver 4,941 acres
Third (this notice)2 November 2026Byramangala, KanchugaranahalliAbout 1,895 acres
TotalAs of 2 November 2026Nine villagesOver 7,335 acres

The three notices together cover the nine villages named in the township plan. The sum of the three stages matches the cumulative figure reported after the latest notice.

Timeline from approval to final notice

  1. January 2025: Cabinet approved the original township proposal, according to one report.
  2. March 2025: GBDA issued a preliminary land acquisition notification proposing 7,481 acres across nine villages. Landowners were to receive 40% of developed land in return for surrendering land rights, according to the GBDA Commissioner.
  3. 7 May 2026: Government approval for the GBIT project was granted.
  4. May 2026: Cabinet approved a revised proposal covering the same extent as the earlier proposal.
  5. June 2026: First final notice, covering three villages.
  6. 15 July 2026: Second final notice, covering four villages.
  7. 2 November 2026: Final notice for about 1,895 acres in Byramangala and Kanchugaranahalli.
  8. 11 November 2026: Reports said the township and the Satellite Town Ring Road were formally approved at a meeting of BMRDA, which is the special purpose vehicle and Local Planning Authority for both projects.

The earlier final notices were issued under Section 19(1) of the Karnataka Urban Development Authorities Act, 1987.

What the notice means for landowners in the two villages

Landowners in Byramangala and Kanchugaranahalli now receive a final notice, which is the step that leads to compensation and possession. The compensation framework is the land acquisition law that applies to the project. Compensation rates per acre have not been announced.

The Karnataka Pranta Raitha Sangha (KPRS) has accused the government of breaking an assurance. Its general secretary, Yashwant T, said the chief minister had assured the project would be kept on hold until a committee submitted its report. Farmers' protest over the acquisition has now entered its 570th day.

The government says that about 80% of farmers support the project. Farmer groups dispute this claim.

Project cost and funding

The government estimate is Rs 18,133 crore, one report gives about Rs 20,000 crore, and another gives about Rs 22,000 crore. The civil works component is estimated at Rs 6,580 crore, and the land acquisition cost is estimated at about Rs 10,000 crore.

HUDCO has offered a loan of up to Rs 21,000 crore for the township. The GBDA Commissioner has said the authority would draw from the loan only as needed. The loan offer is an offer and not a disbursement.

Opposition and open questions

Opposition to the township is based on ecological and livelihood concerns. A social media campaign under the hashtag SaveBidadi was set to start on 1 November 2026.

An NGO, Bidadi Geleyara Balaga, says it asked the National Green Tribunal to take suo motu cognisance of the township's ecological impact, and that the tribunal acknowledged the request. The NGO has also said it would submit details of lakes and forest land to be affected.

Open questions include the compensation rate, the outcome of the government's landowner feedback committee, and whether the project's master plan will change the layout of the nine villages. The master plan was still at the consultant stage when reports were filed.

What buyers should know now

As of November 2026 the township is Upcoming. No BHK types, carpet areas, possession dates or sale prices have been announced. Buyers looking for a home should not treat the final notices as a sign of launch.

The GBDA has floated a Rs 26-crore tender for a consultant to prepare the master plan and Detailed Project Report, with a 12-month engagement. The scope covers road network, parks, civic amenities, and industrial and commercial land parcels.

The township is about 25 km from Bengaluru and is planned to be connected by five major roads. Two of three shortlisted sites for Bengaluru's second international airport are close to the township.

Frequently asked questions

What did the 2 November 2026 GBIT notification decide?

It issued final land acquisition notifications for about 1,895 acres in Byramangala and Kanchugaranahalli villages of Bidadi Hobli, Ramanagara taluk.

Are homes on sale in Bidadi township now?

No homes are on sale yet, because the township is Upcoming as of November 2026 and no BHK types or prices have been announced.

How much land is under final notices so far?

Over 7,335 acres across nine villages, according to reports issued after the 2 November 2026 notification.

Is the Bidadi township still going ahead despite protests?

The government has not paused the project, although farmers' protest has entered its 570th day and a four-member committee has been set up to collect landowner feedback.

What is the cost of the Greater Bengaluru Integrated Township?

Reported cost estimates range from Rs 18,133 crore in the government estimate to about Rs 22,000 crore in one report.